Deck the Halls with Wires and Sawdust, Fa La La La La, La La La La!

Tis the season to be jolly, fa la la la la, la la la la!

Not only is this the season to be jolly, it’s the season to be BUSY! We’ve had some ups and downs, but we are getting a lot done on the house.

When I last posted, we were supposed to have the HVAC contractors, siding guys, and the cabinet guy come the next week. Only one person (Rick from Lensing for the cabinets) showed up on Monday, November 25. He measured and looked like everything was going to work out just great . . . until he left. 😯 Key the drama button. Duh duh duh duh! I got back up to Jill’s house and Bill asked me if I told Rick that we were going to have stone all the way back to the wall on each side of the fireplace. Uh, No!!!! I forgot to tell him that! 😡 I quickly gave Rick a call. Rick had done Jill and Jim’s window seat on one side of their fireplace and kid’s computer desks on the other side. He was going on the basis of how they stopped their stone just around the edge of the fireplace since they had cabinets on each side. We estimated how thick the stone would be and made the window seats shorter than he measured. He was going to draw up plans and send to me for approval before he ordered them. Here is a snapshot of the window seats. I decided to go with drawers instead of doors as I thought we’d use the drawers to store blankets, throws, etc.

Window Seat Drawing by Rick at Lensing

Window Seat Drawing by Rick at Lensing

Tuesday, Nov. 26, the siding guys showed up. The siding had not been delivered yet. That was a blessing in disguise. Turns out the siding guys said they could not install our siding until our electricity was installed. Really? Did no one ever mention that the electricity needed to be installed prior to the siding installed? At one time we were going to have the electricians come right after plumbing but that didn’t happen. The siding guys said that since we were installing flood lights on our fascia, the electricity would have to be run before they could install siding. Jim questioned why they couldn’t start at the bottom of the house and work their way up; but, they said they preferred to wait until all electricity was run. Some things are just meant to be. I believe that is what happened in this case. The siding guys did a few preliminary installs on the corners of the house and called Benthall Brothers (our Hardie cement board distributor) to hold off delivering the siding. And, then they left.

Jim called our electrician to see what his schedule looked like and when he could pencil us in. Fred (electrician) said he was on a big job and had a couple more scheduled after that but probably could not get to us for a couple of weeks – around the second week of December. 😦 Yikes! Everyone was beating their heads thinking we really should have scheduled the electrician before now because we couldn’t move forward until that part was done. But, Bill and I found out there was still lots we could do before he arrived. It was Thanksgiving that week, and I had some Christmas shopping to do, people!

The HVAC guys came back to finish up their rough-in work on Wednesday, Nov. 28. I don’t have many photos of that. Not much to look at but some vents and tubing for the exhaust fans in the bathrooms. What I did take pictures of was the venting done for the kitchen chimney range exhaust fan. Our exhaust fan looks like this.

Our Range Chimney Exhaust Hood

Our Range Chimney Exhaust Hood

So, the HVAC guys decided to vent the exhaust fan down, through the crawl space, and out the side of the house. They said they didn’t want to go all the way up through the roof. So, this is how they roughed in the venting.

Venting the range hood

Venting the range hood

Closer view

Closer view

I kept telling Bill I just didn’t think the venting made sense to me the way it looked. He said something was off. We had a 17″ tall cabinet going above the vented area.  We didn’t think things were right. We decided to wait until after Thanksgiving and see if Bill could figure out if the venting was correct or not.

In the meantime, Bill said for me to be thinking where we might want electrical outlets and switches for our lights and fans. He wanted us to do our own walk-thru and mark where we wanted things placed before our walk-through with Fred the electrician. OMG, making all those decisions was a long and hard process. Yes, we had an electrical floor plan – but that was where light fixtures, can lights, exhaust fans, ceiling fans, and exterior lights would be installed. So, I got out my floor plan from my 3D software which had furniture placed in it to decide where I might want those outlets and cables for digital phone and TV and where I wanted CAT5 cables run for Internet. Bill & I worked on this project several days marking up the house and stapling labels on the studs.

On Tuesday morning, December 3, the fireplace installers arrived. It was great to see the fireplace inside the frame.

Fireplace installation

Fireplace installation

Fireplace inside the frame

Fireplace inside the frame

While the fireplace was being installed we had a planned walk-through meeting with Mark from Wood Specialities by Fehrenbacher. Mark has worked with us for well over a year in creating a custom baseboard, selecting wood trim for our windows and doors, selecting a design for our wooden interior doors, and headband and beam design for the family room ceiling. He gave us some ideas about transitioning from the 9 ft ceiling entry to the vaulted section of the family room. And, we were able to discuss material for a double mantle for the fireplace. He measured everything in the whole house. He said he’d send us a new quote for everything within a week or so. He did ask if we had picked out a stain color yet. I told him I was waiting for our front door to be installed so I could see the color. I wanted the stain color to match our front door and the cabinetry throughout the house. Mark said once we picked out the stain color, he would need some of it to put on the interior door sections that might expand – prior to the painter doing the staining.

Bill called our painter Mark and asked him about stain and how we went about picking out a color. He said he liked using Zar wood stain and asked that we go pick out a color at the Newburgh Benjamin Moore store. We put that on our to-do list.

Our front door had been delivered, but we were waiting on the framing crew to stop by and install it. You couldn’t see what the door looked like because it was totally boxed up. I think it was late the next evening that framer Greg and his crew came and installed our front door and the pocket door mechanism for the master closet.

Pocket Door Mechanism

Pocket Door Mechanism

Front Door Interior View (still has cardboard on it to protect it)

Front Door Interior View (still has cardboard on it to protect it)

Exterior view of the front door (has plastic on the center section)

Exterior view of the front door (has plastic on the center section)

Earlier in the week, Bill got back to looking at the venting for the range fan. He ended up getting the fan out of the box, going through the installation guide, and temporarily tacked it up to where it should be installed to see if the venting the HVAC guys would work. Here’s what he found out.

Range Fan and strange venting

Range Fan and strange venting

The venting wasn’t going to work as it. It needed to go up a lot higher. Bill text Jason the HVAC guy along with the photo above and asked if he would please come by to discuss how it could be changed. And, he said it needed to be changed before insulation was put in. More on this later.

And, while we are talking about HVAC, Jason had asked us a couple of weeks ago if we wanted to take the federal tax credit for the geothermal unit in 2013 or in 2014. The Federal credit was 30% of the cost (with no upper limit) and that included installation of it all, too. Bill and I decided since 2013 would be our craziest year for taxes (Bill retiring, both of us going on Social Security, taking out monthly retirement allocations, Medicare, selling a house, and building a new one), we thought it would be best to use the tax credit for this year. However, to do that, we had to be billed for the geothermal unit and pay for it in 2013! It was December and we had to send in our December construction draw to the bank by December 5 to get money to pay contractors by the 10th. Bill made all the phone calls and did the leg work and got an invoice for everything just in time to turn it in to the bank! Whew!

Then the weather took a dive. Thursday afternoon, December 5, we went from freezing rain to ice to snow. Friday, December 6, it snowed all day. We ended up with over 7 inches of snow. See, it was a huge blessing that the siding was not delivered. That would have been a mess!

Snow storm

Snow storm

Jill & Jim's driveway

Jill & Jim’s driveway

Needless to say we had nothing going on down at the construction site until the following week. During the snow hiatus, Bill was able to work on the cabinets a couple of days. He finished all the drawers and drilled the holes for the handles.

Cabinet drawers

Cabinet drawers

Fred the electrician called and we scheduled our walk through with him for Monday, December 9. He was impressed with all our work we did marking what and where we wanted outlets. He made his markings on the studs as we went from room to room. Oh, and I decided to make the exercise area in the laundry room my computer area instead. 🙂 I made sure we had lots of outlets and cabling for that area. Fred said they would be back on Tuesday or Wednesday to install it all.

In the meantime, Bill had made arrangements with the drywall guy Bart and Les the insulation contractor since they were next up after the electrician in the interior. Bart had to install some drywall on a couple of walls between the kitchen and garage and the laundry room and garage before Les could install foam insulation in those areas. Bart made arrangements to have some drywall sheets delivered. The drywall was delivered on Monday, Dec. 9. Bill called Bart and he said he’d be out as soon as he could.

Jim called the siding guy and told him that the electric had been roughed in. He said they were working on a job and had one or two jobs afterwards. He said it might be Christmas week or after before they would get to us. Then we talked about the possibility of getting the front porch poured before the siding was installed. Jim called the concrete guy to find out his schedule. He said that in the winter they prefer not to “blanket” colored concrete as the finish doesn’t come out as well. So, he said that if the temperatures didn’t get below 26 degrees for 4 days in a row after pouring the concrete, he could pour it for us. So, Jim told us to keep an eye on our weather app.

So, no one showed up on Tuesday, December 10.

The electrical crew arrived on Wednesday the 11th. They were by far the messiest crew we cleaned up after; however, they were the quickest! They installed it all in less than a day! Bill called me when Fred said he couldn’t really install as many can lights above our island as was on the electrical plan. He said they would be too close together. Bill wanted me to come down and “approve” the change. It was a good thing I went down there. I found a couple of things that were not installed correctly. The fewer cans above the island was fine. However, I noticed that where the guys had installed the switches for the lights by each window seat were so low that I would lean on the switch with my back. I asked that they be moved up. And, I also noticed that the vanity lights connections looked too low. I asked Bill if Fred had gone by our spec document for the installation location for the vanities. He said he didn’t know. I grabbed the document which we kept in the house and checked to see where the lights were to be installed. We have tall mirrors for the bathrooms and Bill and I had measured cabinets, granite, backsplash and mirror months ago to determine height of the lights. We talked to Fred and he brought his tape measure and sure enough the lights were about 6 inches too low. Fred had everything fixed before they left.

And, we were wired!

This slideshow requires JavaScript.

The next day the temperatures dipped all day to single digits. Bill and I went down to the house to double-check if all the electrical outlets and switches were correct and in the right location, but it was too cold to do it. So, Bill and I spent the day running errands for the new house. We went to Benthall Brothers to pick out our garage doors; stopped by Fehrenbacher’s to drop off the signed contract and pick up some sample poplar pieces for staining samples; went to the Benjamin Moore paint store with all our samples to match and picked a stain color; and then went to an electrical supply store to buy wiring for Bill to hook up a large portable furnace to use in our house. I guess it was a good day to get all that done. We figured we wouldn’t have any contractor show up on that day!

Friday the 13th Bart came and put up the drywall. And Jason’s crew came and looked at the range exhaust fan venting issue. Turns out they moved it over one stud and went up a lot further. Now, that will work!

Drywall installed along the kitchen/garage wall

Drywall installed along the kitchen/garage wall

Drywall along the laundry room/garage wall

Drywall along the laundry room/garage wall

New location of the venting for the range exhaust fan

New location of the venting for the range exhaust fan

Oh, I forgot to say that when the well guys came several weeks ago they said that there was a little white mold developing in our crawl space. YIKES! 😯 They said we probably needed to get that vapor barrier installed ASAP. Of course, the hold-up was waiting until the electric was run. Not that it was done, that barrier needed to get down. But, it was cold and nasty out. This was one PITA job Bill didn’t want to do. I didn’t want him to do it either. I told him to call a company does that and have them install it. We both checked out companies on the Internet and Bill sent an email to one to inquire what it would cost. They called. They said it would cost approximately $2K. Bill said he didn’t want to pay that much. Ugh!

Jim said he knew a recent college grad who worked construction while he was off from school. He asked if Bill wanted him to call and see if he would be interested in working for us. YES!!! Do not stop. Do not pass Go. Just call him right away! And, so he did. Todd said he’d be interested in working for us for several days. He started working last week. He cleaned up the garage and cleaned and vacuumed the house in preparation for the insulation crew on Tuesday and Wednesday for a couple of hours. They were coming Thursday, December 19.

We found out Monday that the temps were going to be soaring up into the 40s, 50s and even the 60s that week. Jim said it looked like they could pour the front porch! But, wait. We hadn’t picked out a color yet for the colored concrete. Where and how were we supposed to get that information? Jim said he’d get a brochure from Tony the concrete guy. Monday evening Jim brought home the brochure. He said if we could make a decision of what color by early Tuesday, he would call Tony and they could hopefully pour the concrete on Wednesday or Thursday. Bill looked at the brochure and picked Colonial Red. I said, “No Way!” The color decision was up to me.

I had a doctor’s appointment early Tuesday morning so I made arrangements to stop by the stone place so I could match up a concrete with our stone selection. With Rick the stone guy’s advice, I went with a lighter color than I originally wanted. He said from experience he said the darker colors show dirt and scratches more. So, I picked Sandstone for the colored concrete. I called Bill and he text Jim the color and said we wanted a smooth finish. Bill also asked if Tony could add some grit to the sealer so the concrete wouldn’t be as slippery when wet. He said he could!

Earlier in the week Bill and I went through the house to see about all the electrical stuff. We found a couple of outlets missing. And I decided to change the under-cabinet outlet wiring in the corner of the kitchen cabinets to a wall outlet. After doing some reading I found that for the appliances that people like to keep plugged in all the time (i.e., coffee pot) having the cords hanging down wasn’t a preference. So, the only appliance that Bill and I keep plugged in is the coffee pot and we had planned on keeping it in the corner. And, I discovered I had made a mistake and had the master bathroom outlets on each side of the vanity placed wrong. The hand towels would cover up the outlet. We wanted those moved. Bill called Fred and gave him a list of things and he said they’d be back out later in the week. The electrical crew came back on Wednesday and had everything done in 20 minutes! I’m telling you, these guys are fast!

Undercabinet wiring changed to outlet in kitchen corner cabinet area

Under-cabinet wiring changed to outlet in kitchen corner cabinet area

We did mess up on our labeling for the new computer area in the multi-purpose laundry room. Originally we thought we’d put two can lights above the area and had that on our label. But, when we were going room to room, I decided to move a nicer ceiling light I had originally purchased for the hall bathroom to our master closet. The master closet originally was going to have a flush mounted ceiling light just like the three in the laundry room. So, we decided we would just put that flush mounted light above the computer area. However, before the electrician’s came to install, we scratched out can lights and changed to ceiling light on the label, but forgot to scratch out the #2. So, the electricians ran two ceiling lights above the computer area. Instead of having them remove one of them, I decided to buy two smaller versions of the mounted ceiling lights – they were cheap at Menards. That way we have a spare light if anything breaks. 🙂

We had a full house at the site on Thursday, December 19. Les came with his insulation crew.

Netting with fiberglass blown in on all exterior walls and under the attic floor

Netting with fiberglass blown in on all exterior walls and under the attic floor

Spray foam up in the vaulted area of the family room

Spray foam up in the vaulted area of the family room and along the walls where the drywall was tacked up

Workers spraying 2" of the foam on all exterior walls prior to installing the netting and blowing in the fiberglass insulation

Workers spraying 2″ of the foam on all exterior walls prior to installing the netting and blowing in the fiberglass insulation

Fiberglass insulation all around that fireplace and exterior wall

Fiberglass insulation all around that fireplace and exterior wall

Sound barrier insulation between the family room and master bedroom

Sound barrier insulation between the family room and master bedroom

Sound barrier between the master bedroom and master bathroom

Sound barrier between the master bedroom and master bathroom

Sound barrier between the kitchen and laundry room walls

Sound barrier between the kitchen and laundry room walls

Tony and his crew came on Thursday, too, and poured the front porch.

Tony setting up for the concrete

Tony setting up for the concrete

Porch poured

Porch poured

Close-up of front porch

Close-up of front porch

I hope the color is going to be okay. He said we really won’t know the final color until the concrete is sealed. He said they cannot seal it for at least seven days. I’ll keep my fingers crossed that it will all match.

Bill called Todd in the afternoon since he had not shown up yet. There was a communication error. Todd thought Bill was supposed to call him when he wanted him to come out. So, Todd worked really late Thursday night in the crawl space. He also worked most of the day Friday, too. He is just about done installing the vapor barrier. Bill said he is doing a great job. He is supposed to come back today and clean all the mold with Borax and then he will be done. All the snow and ice melting last week from the high temps and 4 inches of rain over the weekend has caused a muddy mess down at the construction site.

Bill spent the weekend putting up blocking for anything we might hang – pictures, cabinets, TVs, grab bars, towel racks, etc.

IMG_3191

IMG_3194IMG_3192

With the holidays approaching we are not sure if anyone will be working this week or next. I guess we will see what Santa brings our way.

We Are Thankful!

A dream doesn’t become reality through magic; it takes sweat, determination and hard work. ~Colin Powell

Our dream home is becoming a reality! And, boy is it taking a lot of sweat, determination and hard work!

This is a time to be thankful! We are thankful to everyone who is making this dream happen for Bill and me. We are thankful for God providing us with the means to find and purchase this lovely piece of land to share with our family. We are thankful for our son Bryan who is encouraging us from afar in this venture even though he won’t be living close by. We are thankful for Jill and Jim for giving us a place to live while we are building. We are thankful for Jim who is spearheading the construction of our home and finding all those little things that we might not even think of because we don’t have that knowledge to find those things! We are thankful for Jill who is handling the financial side of the construction by keeping up with the bills and software! We are also thankful to Jill for helping us envision how things will look and honestly telling us if something doesn’t look right. We are thankful for Jim, Sr. and Joan for letting us use their construction company for this endeavor. We are thankful for Jim, Sr.’s advise and expertise in structural engineering. We are thankful for having great subcontractors so far! And, lastly, I am thankful for Bill – who has worked over and above on this project by doing all the PITA jobs, keeping contact with all the subs via email and phone, cleaning the construction site, burning the excess wood, and working on the cabinets when he has time in-between all the other jobs.

We’ve had a lot of progress since I last posted. The framers thought they were going to finish on Wednesday, Nov. 13, so Bill scheduled the roofer to come on Friday, Nov. 15. Well, the framers worked long hours into the dark several days but didn’t finish until Friday afternoon. We had a full house on Friday with the 5-man framing crew, a large roofing crew, and the roofing material company delivering the shingles. In addition, the HVAC and insulation guys came out to do walk-thru’s. And, of course, each of these people drove their own cars or trucks. They were parked all along our driveway and Jill and Jim’s driveway. Here are some pictures of the exterior framing.

Framing the back roof line

Framing the back roof line

Framing the west side of the house

Framing the west side of the house

This shows how high the hip roof goes from the front

This shows how high the hip roof goes from the front

Looking up toward the roof from inside the family room, I was amazed how much space was above the kitchen and laundry room. This space would haunt me later. 😡

Attic space above kitchen and laundry

Attic space above kitchen and laundry

Roof line looking toward the front door

Roof line looking toward the front door

I loved when the framers put the sheet rock on the roof. Finally, I thought the exterior of the house looked like the elevation drawings of the house that Jim drew up for us. This is what the guys got done by the end of Wednesday, Nov. 13.

This slideshow requires JavaScript.

It was suggested we install some weather-stripping prior to the framers installing the windows. Alrighty then, who installs that? Hmmmmmm. While the framers finished the roof, Bill worked on his next PITA job – installing the weather-stripping. Bill did say it wasn’t that bad of a job.

Bill showing off his work.

Bill showing off his work.

Weather stripping close up

Weather stripping close up

Thursday, Nov. 14, the framers installed our windows. Those went in really quick.

Windows going in

Windows going in

West wall

West wall

Close up of triple window in front bedroom

Close up of triple window in front bedroom

Rear of home

Rear of home

Preparing for the triple garage window

Preparing for the triple garage window

We had to go over with Greg (the framer) the height we wanted our vault to go in the family room and bedroom. Greg put up a board in the master bedroom to get my approval. The height on the flat center turned out to be about 10-1/2 ft high. Perfect! The vault would go up 18 inches from the 9 foot ceiling.

Board where the flat part of the vaulted ceiling would go in the master bedroom.

Board where the flat part of the vaulted ceiling would go in the master bedroom.

And, this is what the shape will look like. Imagine drywall up there. We wanted some extra height in the master bedroom as we have a large wooden canopy king bed going in there without it feeling dwarfed. Time will tell!

Master Bedroom vaulted ceiling with flat center

Master Bedroom vaulted ceiling with flat center

The other things on the framer’s list to complete on Thursday was the Family Room ceiling, the master walk-in shower bench, and building the fireplace structure.

Family Room vaulted ceiling

Family Room vaulted ceiling

The Family Room flat section goes up to about 14-1/2 feet.

Master bathroom shower bench

Master bathroom shower bench

This is my favorite photo of the unfinished house so far. It’s the fireplace flanked by two eventual window seats and the vaulted with flat ceiling. I can’t wait to see how this will turn out cause I already like the shape it’s taking on.

Fireplace structure

Fireplace structure

Friday, Nov. 15, the roofers and framers were hammering away in the very early morning.

This slideshow requires JavaScript.

Bill picked up all the excess wood that he couldn’t use and burned away.

Lots to burn

Lots to burn

By the end of Friday we had the framing and roofing completed . . . or so we thought! 😕

Saturday afternoon, Nov. 16, and Sunday, Nov. 17, Bill and I swept and vacuumed the interior of the house. We had to lay out, measure, and mark all the cabinets and appliances on the floor before the plumbers and HVAC guys came on Monday morning. It was a lot of work but also exciting to see if everything would fit the way we thought it should. Bill had built our cabinets prior to the house being framed, so we had to make sure everything was going to fit!

Looking from the family room toward the kitchen

Looking from the family room toward the kitchen

Looking from the family room toward the dining area on the left and kitchen to the right

Looking from the family room toward the dining area on the left and kitchen to the right

Looking toward the front door

Looking toward the front door

Looking from the family room to the hall closet on the right of the entryway

Looking from the family room to the hall closet on the right of the entryway

Looking through the wall that separates the family room and the master bedroom

Looking through the wall that separates the family room and the master bedroom

Let me back up a little here. Thursday, Rick from Lensing (where we are getting our bathroom vanities/cabinetry) came to measure. The framing wasn’t all complete (one of the walls for the window seat wasn’t done yet), but he came anyway. I wasn’t there. He told Bill that in our hall bath we would have to go with 18 inch depth cabinetry as there was not enough room for the 22 inch for which we had originally planned. 😯 Bill and I re-measured the bathroom during the weekend to see if it was framed correctly. We came up with the same measurements that were on our plan. How could this have happened? We knew the bathroom was going to be tight but I had 22 inch deep vanities in my 3D software and they fit and Jim had 22 inch standard vanities in his drawings. Something was off. The master bedroom closet was right behind this bathroom. I was willing to give up three to four inches if that wall could be moved. But, looking up, it appeared that the ceiling joists were laying right on the top of that wall. We figured it could not be moved without a lot of difficulty. Crud!

I didn’t know what to do. I really didn’t want 18 inch deep cabinets. Jill said maybe we could go with a standalone furniture-like vanity if they came in that depth. Jill said she would talk to Jim and have him look at the bathroom and see if he could see what options we might have. In the meantime, Bill and I went out to Lowe’s Saturday evening and looked at 18 inch depth cabinets. There weren’t many but I thought if that is what we had to do, then that would be what we would have built. However, I would have to get rid of the full-size cabinet next to the vanity. It would close in the bathroom too much.

Sunday, Jim walked through the house to see if everything was framed correctly. Jim, Sr. came over and we gave him his first tour of the house. Jim, Sr. made a comment that our beam that separates the kitchen/dining area from the family room was one big beam! And, I kept looking up at all that space up there, saying that I guess we should have thought about that space before. You could stand up in that space. I verbalized to both Jims and Bill that maybe we should have put a room up there. I had mentioned the space to Jill earlier, too. Even if we gave up part of the laundry room to build a staircase up there, she asked if I would really want to go up there without a window? Jim said if we wanted to do something with the space, now was the time. My head was spinning.

Should we make attic into a bonus room?

Should we make attic into a bonus room?

Jim and Bill climbed up the attic stairs and walked up in the area above the kitchen and laundry. Jim finally said, yes there would be enough room to make about a 14×14 room with slanted walls. He then asked if we wanted to spend about $15-20K to make it happen. And, I still wouldn’t have a window! Finally, I said, it’s not worth it. I also said that soon the drywall would be up and I wouldn’t look up at it and wonder. Besides, Bill and I said . . . this house would have no stairs. And, I wasn’t willing to give up my laundry room.

Once that was decided, we moved along. We had to see about that hall bathroom. The guys got to re-measuring the room and found that it was framed correctly. However, Jim discovered that the bathroom door had been placed in the wrong place. Jim said we had a couple of options. If we wanted to leave the door where it was and move the wall back into part of the closet space, we would have to check with the framer to see if the wall could be moved. Or, the easier thing would be to check with the plumber to see how deep the tub enclosure was going to be so we would know how many inches to have the framers move the door over. Bill decided to check with the plumber the next day.

Jim, Sr. said we really needed more support for that big old beam by the entry door from the garage. He said we didn’t want it to eventually sag. Bill discovered that the wall to divide the dining area from the family room was only 10 inches and it was supposed to be 2 ft 2 inches. Jim looked at the fireplace structure and asked Bill why the one support was so high up and then when Bill got out the instructions, they discovered a section had not been built. Bill said he would call Greg the framer later in the week to update him once we knew what we were going to do in that bathroom. Honestly, we decided that if these were the only things that were wrong in the whole house, we were in good shape. The framers had done an awesome job and we were pleased. And, Greg had told us he would be working close by and would come back and install the exterior doors as soon as they came in. These extras could be a “rainy day” for them.

Monday, Nov. 18, the plumbers and the HVAC guy came. The HVAC left aluminum pieces to where he thought vents should go. Bill and I had to go through the house and move the vents to where we wanted them to be installed when they came back. Thank goodness I had already placed my furniture in our 3D house planning software so I knew where I could move the vents.

Vent in the entry way

Vent in the entry way

Vent in the front bedroom

Vent in the front bedroom

I told Bill I wanted the vents by the window seats to be installed in the toe-kick of the window seats. Bill had never seen that before. I showed him this picture and said that is what I wanted. He will tell the HVAC guys when they return Monday, the 25th.

Vents in the window seat toe-kick

Vents in the window seat toe-kick

The plumbers did all their rough-in work last week. And, they installed the tub enclosure in the hall bath. Turned out the tub enclosure was an inch deeper than we thought it would be. Which made things even more challenging. If we moved the bathroom door, it would only give us an extra inch. Things weren’t working in our favor. So, we decided to make the bathroom door a 28 inch door instead of a 30 inch door. Our master bathroom door is 36 inches. That’s the one that is most important. The bathroom we are using in Jill’s bonus area has a 28 inch door and it works fine for us. So, by going with a smaller door and probably use a slightly less wide trim inside the bathroom, we can have a 20 inch deep vanity. I called the granite place to make sure the sink we purchased will fit with the smaller depth cabinet. It will. Whew! In addition to the tub enclosure being deeper, the framer was going to have to either move the wall back from the adjoining linen closet (so we had a wall to attach drywall) or make a fake wall right behind it. Again, we saw problems with moving the closet wall because it was supporting ceiling joists.  Here’s what we changed the cabinets in the hall bath to look like:

Hall bath cabinetry

Hall bath cabinetry

Here are photos of the plumbing work.

This slideshow requires JavaScript.

The well guys came back out this past week, too, and trenched and installed pipe from the well to the house. The framers ended up coming back out and fixed all our tweaks and did it in two hours. And, they installed our exterior laundry room door, too! Yay, Framers!!!!

Laundry room exterior door installed

Laundry room exterior door installed

Extra support for the big old beam

Extra support for the big old beam

Door frame changed in hall bath

Door frame changed in hall bath

Installed a fake wall behind the linen closet wall so they could hang drywall.

Installed a fake wall behind the linen closet wall so they could hang drywall.

Extended the window seat dividing wall to 2 ft 2 in

Extended the window seat dividing wall to 2 ft 2 in

Built the extra frame for the fireplace. It will be added to the structure after the fireplace is installed

Built the extra frame for the fireplace. It will be added to the structure after the fireplace is installed

Yesterday, I ended up sweeping up all the piles the plumbers left throughout the house like below.

Piles left by the plumbers

Piles left by the plumbers

Monday the HVAC guys are supposed to be back to make any exterior openings they need to do. Because either Monday or Tuesday, the Hardie Board siding is being installed. Monday, I have Rick from Lensing coming back to do final measuring for the bathrooms and window seats so we can place the order. We’ve decided to go with the brandywine finish for the cabinets as it matches the mahogany Bill is using for the kitchen cabinets.

The front door and the fireplace both got delayed. They were supposed to be installed this past week, but now both will supposedly be installed the week after Thanksgiving.

I’ve spent some time looking at materials for the kitchen backsplash. We are getting closer to making that decision. I’m leaning toward glossy tan subway tiles. We also got our granite samples and they match real well with the cabinets and tile we picked out for the two bathrooms. And, I had to purchase another two light fixtures. I wanted to have a light for each of the window seats. I order two more of the same sconces I had already purchased. Two will be in the interior of the entry way and the other two will be in the window seats.

Entry Sconces and Window Seat Sconces

Entry Sconces and Window Seat Sconces

And, I’m thinking I may just change the spot for the exercise bikes in the laundry room to my computer area. 😆 I’ll probably be on the computer way more than I’ll be on that bike. And, the view is so nice and I’d have my own space.

Future computer area

Future computer area

We are taking each day as it comes and doing what we can to make decisions and adjustments. So far it’s all been GOOD!