Deck the Halls with Wires and Sawdust, Fa La La La La, La La La La!

Tis the season to be jolly, fa la la la la, la la la la!

Not only is this the season to be jolly, it’s the season to be BUSY! We’ve had some ups and downs, but we are getting a lot done on the house.

When I last posted, we were supposed to have the HVAC contractors, siding guys, and the cabinet guy come the next week. Only one person (Rick from Lensing for the cabinets) showed up on Monday, November 25. He measured and looked like everything was going to work out just great . . . until he left. 😯 Key the drama button. Duh duh duh duh! I got back up to Jill’s house and Bill asked me if I told Rick that we were going to have stone all the way back to the wall on each side of the fireplace. Uh, No!!!! I forgot to tell him that! 😡 I quickly gave Rick a call. Rick had done Jill and Jim’s window seat on one side of their fireplace and kid’s computer desks on the other side. He was going on the basis of how they stopped their stone just around the edge of the fireplace since they had cabinets on each side. We estimated how thick the stone would be and made the window seats shorter than he measured. He was going to draw up plans and send to me for approval before he ordered them. Here is a snapshot of the window seats. I decided to go with drawers instead of doors as I thought we’d use the drawers to store blankets, throws, etc.

Window Seat Drawing by Rick at Lensing

Window Seat Drawing by Rick at Lensing

Tuesday, Nov. 26, the siding guys showed up. The siding had not been delivered yet. That was a blessing in disguise. Turns out the siding guys said they could not install our siding until our electricity was installed. Really? Did no one ever mention that the electricity needed to be installed prior to the siding installed? At one time we were going to have the electricians come right after plumbing but that didn’t happen. The siding guys said that since we were installing flood lights on our fascia, the electricity would have to be run before they could install siding. Jim questioned why they couldn’t start at the bottom of the house and work their way up; but, they said they preferred to wait until all electricity was run. Some things are just meant to be. I believe that is what happened in this case. The siding guys did a few preliminary installs on the corners of the house and called Benthall Brothers (our Hardie cement board distributor) to hold off delivering the siding. And, then they left.

Jim called our electrician to see what his schedule looked like and when he could pencil us in. Fred (electrician) said he was on a big job and had a couple more scheduled after that but probably could not get to us for a couple of weeks – around the second week of December. 😦 Yikes! Everyone was beating their heads thinking we really should have scheduled the electrician before now because we couldn’t move forward until that part was done. But, Bill and I found out there was still lots we could do before he arrived. It was Thanksgiving that week, and I had some Christmas shopping to do, people!

The HVAC guys came back to finish up their rough-in work on Wednesday, Nov. 28. I don’t have many photos of that. Not much to look at but some vents and tubing for the exhaust fans in the bathrooms. What I did take pictures of was the venting done for the kitchen chimney range exhaust fan. Our exhaust fan looks like this.

Our Range Chimney Exhaust Hood

Our Range Chimney Exhaust Hood

So, the HVAC guys decided to vent the exhaust fan down, through the crawl space, and out the side of the house. They said they didn’t want to go all the way up through the roof. So, this is how they roughed in the venting.

Venting the range hood

Venting the range hood

Closer view

Closer view

I kept telling Bill I just didn’t think the venting made sense to me the way it looked. He said something was off. We had a 17″ tall cabinet going above the vented area.  We didn’t think things were right. We decided to wait until after Thanksgiving and see if Bill could figure out if the venting was correct or not.

In the meantime, Bill said for me to be thinking where we might want electrical outlets and switches for our lights and fans. He wanted us to do our own walk-thru and mark where we wanted things placed before our walk-through with Fred the electrician. OMG, making all those decisions was a long and hard process. Yes, we had an electrical floor plan – but that was where light fixtures, can lights, exhaust fans, ceiling fans, and exterior lights would be installed. So, I got out my floor plan from my 3D software which had furniture placed in it to decide where I might want those outlets and cables for digital phone and TV and where I wanted CAT5 cables run for Internet. Bill & I worked on this project several days marking up the house and stapling labels on the studs.

On Tuesday morning, December 3, the fireplace installers arrived. It was great to see the fireplace inside the frame.

Fireplace installation

Fireplace installation

Fireplace inside the frame

Fireplace inside the frame

While the fireplace was being installed we had a planned walk-through meeting with Mark from Wood Specialities by Fehrenbacher. Mark has worked with us for well over a year in creating a custom baseboard, selecting wood trim for our windows and doors, selecting a design for our wooden interior doors, and headband and beam design for the family room ceiling. He gave us some ideas about transitioning from the 9 ft ceiling entry to the vaulted section of the family room. And, we were able to discuss material for a double mantle for the fireplace. He measured everything in the whole house. He said he’d send us a new quote for everything within a week or so. He did ask if we had picked out a stain color yet. I told him I was waiting for our front door to be installed so I could see the color. I wanted the stain color to match our front door and the cabinetry throughout the house. Mark said once we picked out the stain color, he would need some of it to put on the interior door sections that might expand – prior to the painter doing the staining.

Bill called our painter Mark and asked him about stain and how we went about picking out a color. He said he liked using Zar wood stain and asked that we go pick out a color at the Newburgh Benjamin Moore store. We put that on our to-do list.

Our front door had been delivered, but we were waiting on the framing crew to stop by and install it. You couldn’t see what the door looked like because it was totally boxed up. I think it was late the next evening that framer Greg and his crew came and installed our front door and the pocket door mechanism for the master closet.

Pocket Door Mechanism

Pocket Door Mechanism

Front Door Interior View (still has cardboard on it to protect it)

Front Door Interior View (still has cardboard on it to protect it)

Exterior view of the front door (has plastic on the center section)

Exterior view of the front door (has plastic on the center section)

Earlier in the week, Bill got back to looking at the venting for the range fan. He ended up getting the fan out of the box, going through the installation guide, and temporarily tacked it up to where it should be installed to see if the venting the HVAC guys would work. Here’s what he found out.

Range Fan and strange venting

Range Fan and strange venting

The venting wasn’t going to work as it. It needed to go up a lot higher. Bill text Jason the HVAC guy along with the photo above and asked if he would please come by to discuss how it could be changed. And, he said it needed to be changed before insulation was put in. More on this later.

And, while we are talking about HVAC, Jason had asked us a couple of weeks ago if we wanted to take the federal tax credit for the geothermal unit in 2013 or in 2014. The Federal credit was 30% of the cost (with no upper limit) and that included installation of it all, too. Bill and I decided since 2013 would be our craziest year for taxes (Bill retiring, both of us going on Social Security, taking out monthly retirement allocations, Medicare, selling a house, and building a new one), we thought it would be best to use the tax credit for this year. However, to do that, we had to be billed for the geothermal unit and pay for it in 2013! It was December and we had to send in our December construction draw to the bank by December 5 to get money to pay contractors by the 10th. Bill made all the phone calls and did the leg work and got an invoice for everything just in time to turn it in to the bank! Whew!

Then the weather took a dive. Thursday afternoon, December 5, we went from freezing rain to ice to snow. Friday, December 6, it snowed all day. We ended up with over 7 inches of snow. See, it was a huge blessing that the siding was not delivered. That would have been a mess!

Snow storm

Snow storm

Jill & Jim's driveway

Jill & Jim’s driveway

Needless to say we had nothing going on down at the construction site until the following week. During the snow hiatus, Bill was able to work on the cabinets a couple of days. He finished all the drawers and drilled the holes for the handles.

Cabinet drawers

Cabinet drawers

Fred the electrician called and we scheduled our walk through with him for Monday, December 9. He was impressed with all our work we did marking what and where we wanted outlets. He made his markings on the studs as we went from room to room. Oh, and I decided to make the exercise area in the laundry room my computer area instead. 🙂 I made sure we had lots of outlets and cabling for that area. Fred said they would be back on Tuesday or Wednesday to install it all.

In the meantime, Bill had made arrangements with the drywall guy Bart and Les the insulation contractor since they were next up after the electrician in the interior. Bart had to install some drywall on a couple of walls between the kitchen and garage and the laundry room and garage before Les could install foam insulation in those areas. Bart made arrangements to have some drywall sheets delivered. The drywall was delivered on Monday, Dec. 9. Bill called Bart and he said he’d be out as soon as he could.

Jim called the siding guy and told him that the electric had been roughed in. He said they were working on a job and had one or two jobs afterwards. He said it might be Christmas week or after before they would get to us. Then we talked about the possibility of getting the front porch poured before the siding was installed. Jim called the concrete guy to find out his schedule. He said that in the winter they prefer not to “blanket” colored concrete as the finish doesn’t come out as well. So, he said that if the temperatures didn’t get below 26 degrees for 4 days in a row after pouring the concrete, he could pour it for us. So, Jim told us to keep an eye on our weather app.

So, no one showed up on Tuesday, December 10.

The electrical crew arrived on Wednesday the 11th. They were by far the messiest crew we cleaned up after; however, they were the quickest! They installed it all in less than a day! Bill called me when Fred said he couldn’t really install as many can lights above our island as was on the electrical plan. He said they would be too close together. Bill wanted me to come down and “approve” the change. It was a good thing I went down there. I found a couple of things that were not installed correctly. The fewer cans above the island was fine. However, I noticed that where the guys had installed the switches for the lights by each window seat were so low that I would lean on the switch with my back. I asked that they be moved up. And, I also noticed that the vanity lights connections looked too low. I asked Bill if Fred had gone by our spec document for the installation location for the vanities. He said he didn’t know. I grabbed the document which we kept in the house and checked to see where the lights were to be installed. We have tall mirrors for the bathrooms and Bill and I had measured cabinets, granite, backsplash and mirror months ago to determine height of the lights. We talked to Fred and he brought his tape measure and sure enough the lights were about 6 inches too low. Fred had everything fixed before they left.

And, we were wired!

This slideshow requires JavaScript.

The next day the temperatures dipped all day to single digits. Bill and I went down to the house to double-check if all the electrical outlets and switches were correct and in the right location, but it was too cold to do it. So, Bill and I spent the day running errands for the new house. We went to Benthall Brothers to pick out our garage doors; stopped by Fehrenbacher’s to drop off the signed contract and pick up some sample poplar pieces for staining samples; went to the Benjamin Moore paint store with all our samples to match and picked a stain color; and then went to an electrical supply store to buy wiring for Bill to hook up a large portable furnace to use in our house. I guess it was a good day to get all that done. We figured we wouldn’t have any contractor show up on that day!

Friday the 13th Bart came and put up the drywall. And Jason’s crew came and looked at the range exhaust fan venting issue. Turns out they moved it over one stud and went up a lot further. Now, that will work!

Drywall installed along the kitchen/garage wall

Drywall installed along the kitchen/garage wall

Drywall along the laundry room/garage wall

Drywall along the laundry room/garage wall

New location of the venting for the range exhaust fan

New location of the venting for the range exhaust fan

Oh, I forgot to say that when the well guys came several weeks ago they said that there was a little white mold developing in our crawl space. YIKES! 😯 They said we probably needed to get that vapor barrier installed ASAP. Of course, the hold-up was waiting until the electric was run. Not that it was done, that barrier needed to get down. But, it was cold and nasty out. This was one PITA job Bill didn’t want to do. I didn’t want him to do it either. I told him to call a company does that and have them install it. We both checked out companies on the Internet and Bill sent an email to one to inquire what it would cost. They called. They said it would cost approximately $2K. Bill said he didn’t want to pay that much. Ugh!

Jim said he knew a recent college grad who worked construction while he was off from school. He asked if Bill wanted him to call and see if he would be interested in working for us. YES!!! Do not stop. Do not pass Go. Just call him right away! And, so he did. Todd said he’d be interested in working for us for several days. He started working last week. He cleaned up the garage and cleaned and vacuumed the house in preparation for the insulation crew on Tuesday and Wednesday for a couple of hours. They were coming Thursday, December 19.

We found out Monday that the temps were going to be soaring up into the 40s, 50s and even the 60s that week. Jim said it looked like they could pour the front porch! But, wait. We hadn’t picked out a color yet for the colored concrete. Where and how were we supposed to get that information? Jim said he’d get a brochure from Tony the concrete guy. Monday evening Jim brought home the brochure. He said if we could make a decision of what color by early Tuesday, he would call Tony and they could hopefully pour the concrete on Wednesday or Thursday. Bill looked at the brochure and picked Colonial Red. I said, “No Way!” The color decision was up to me.

I had a doctor’s appointment early Tuesday morning so I made arrangements to stop by the stone place so I could match up a concrete with our stone selection. With Rick the stone guy’s advice, I went with a lighter color than I originally wanted. He said from experience he said the darker colors show dirt and scratches more. So, I picked Sandstone for the colored concrete. I called Bill and he text Jim the color and said we wanted a smooth finish. Bill also asked if Tony could add some grit to the sealer so the concrete wouldn’t be as slippery when wet. He said he could!

Earlier in the week Bill and I went through the house to see about all the electrical stuff. We found a couple of outlets missing. And I decided to change the under-cabinet outlet wiring in the corner of the kitchen cabinets to a wall outlet. After doing some reading I found that for the appliances that people like to keep plugged in all the time (i.e., coffee pot) having the cords hanging down wasn’t a preference. So, the only appliance that Bill and I keep plugged in is the coffee pot and we had planned on keeping it in the corner. And, I discovered I had made a mistake and had the master bathroom outlets on each side of the vanity placed wrong. The hand towels would cover up the outlet. We wanted those moved. Bill called Fred and gave him a list of things and he said they’d be back out later in the week. The electrical crew came back on Wednesday and had everything done in 20 minutes! I’m telling you, these guys are fast!

Undercabinet wiring changed to outlet in kitchen corner cabinet area

Under-cabinet wiring changed to outlet in kitchen corner cabinet area

We did mess up on our labeling for the new computer area in the multi-purpose laundry room. Originally we thought we’d put two can lights above the area and had that on our label. But, when we were going room to room, I decided to move a nicer ceiling light I had originally purchased for the hall bathroom to our master closet. The master closet originally was going to have a flush mounted ceiling light just like the three in the laundry room. So, we decided we would just put that flush mounted light above the computer area. However, before the electrician’s came to install, we scratched out can lights and changed to ceiling light on the label, but forgot to scratch out the #2. So, the electricians ran two ceiling lights above the computer area. Instead of having them remove one of them, I decided to buy two smaller versions of the mounted ceiling lights – they were cheap at Menards. That way we have a spare light if anything breaks. 🙂

We had a full house at the site on Thursday, December 19. Les came with his insulation crew.

Netting with fiberglass blown in on all exterior walls and under the attic floor

Netting with fiberglass blown in on all exterior walls and under the attic floor

Spray foam up in the vaulted area of the family room

Spray foam up in the vaulted area of the family room and along the walls where the drywall was tacked up

Workers spraying 2" of the foam on all exterior walls prior to installing the netting and blowing in the fiberglass insulation

Workers spraying 2″ of the foam on all exterior walls prior to installing the netting and blowing in the fiberglass insulation

Fiberglass insulation all around that fireplace and exterior wall

Fiberglass insulation all around that fireplace and exterior wall

Sound barrier insulation between the family room and master bedroom

Sound barrier insulation between the family room and master bedroom

Sound barrier between the master bedroom and master bathroom

Sound barrier between the master bedroom and master bathroom

Sound barrier between the kitchen and laundry room walls

Sound barrier between the kitchen and laundry room walls

Tony and his crew came on Thursday, too, and poured the front porch.

Tony setting up for the concrete

Tony setting up for the concrete

Porch poured

Porch poured

Close-up of front porch

Close-up of front porch

I hope the color is going to be okay. He said we really won’t know the final color until the concrete is sealed. He said they cannot seal it for at least seven days. I’ll keep my fingers crossed that it will all match.

Bill called Todd in the afternoon since he had not shown up yet. There was a communication error. Todd thought Bill was supposed to call him when he wanted him to come out. So, Todd worked really late Thursday night in the crawl space. He also worked most of the day Friday, too. He is just about done installing the vapor barrier. Bill said he is doing a great job. He is supposed to come back today and clean all the mold with Borax and then he will be done. All the snow and ice melting last week from the high temps and 4 inches of rain over the weekend has caused a muddy mess down at the construction site.

Bill spent the weekend putting up blocking for anything we might hang – pictures, cabinets, TVs, grab bars, towel racks, etc.

IMG_3191

IMG_3194IMG_3192

With the holidays approaching we are not sure if anyone will be working this week or next. I guess we will see what Santa brings our way.

We Are Thankful!

A dream doesn’t become reality through magic; it takes sweat, determination and hard work. ~Colin Powell

Our dream home is becoming a reality! And, boy is it taking a lot of sweat, determination and hard work!

This is a time to be thankful! We are thankful to everyone who is making this dream happen for Bill and me. We are thankful for God providing us with the means to find and purchase this lovely piece of land to share with our family. We are thankful for our son Bryan who is encouraging us from afar in this venture even though he won’t be living close by. We are thankful for Jill and Jim for giving us a place to live while we are building. We are thankful for Jim who is spearheading the construction of our home and finding all those little things that we might not even think of because we don’t have that knowledge to find those things! We are thankful for Jill who is handling the financial side of the construction by keeping up with the bills and software! We are also thankful to Jill for helping us envision how things will look and honestly telling us if something doesn’t look right. We are thankful for Jim, Sr. and Joan for letting us use their construction company for this endeavor. We are thankful for Jim, Sr.’s advise and expertise in structural engineering. We are thankful for having great subcontractors so far! And, lastly, I am thankful for Bill – who has worked over and above on this project by doing all the PITA jobs, keeping contact with all the subs via email and phone, cleaning the construction site, burning the excess wood, and working on the cabinets when he has time in-between all the other jobs.

We’ve had a lot of progress since I last posted. The framers thought they were going to finish on Wednesday, Nov. 13, so Bill scheduled the roofer to come on Friday, Nov. 15. Well, the framers worked long hours into the dark several days but didn’t finish until Friday afternoon. We had a full house on Friday with the 5-man framing crew, a large roofing crew, and the roofing material company delivering the shingles. In addition, the HVAC and insulation guys came out to do walk-thru’s. And, of course, each of these people drove their own cars or trucks. They were parked all along our driveway and Jill and Jim’s driveway. Here are some pictures of the exterior framing.

Framing the back roof line

Framing the back roof line

Framing the west side of the house

Framing the west side of the house

This shows how high the hip roof goes from the front

This shows how high the hip roof goes from the front

Looking up toward the roof from inside the family room, I was amazed how much space was above the kitchen and laundry room. This space would haunt me later. 😡

Attic space above kitchen and laundry

Attic space above kitchen and laundry

Roof line looking toward the front door

Roof line looking toward the front door

I loved when the framers put the sheet rock on the roof. Finally, I thought the exterior of the house looked like the elevation drawings of the house that Jim drew up for us. This is what the guys got done by the end of Wednesday, Nov. 13.

This slideshow requires JavaScript.

It was suggested we install some weather-stripping prior to the framers installing the windows. Alrighty then, who installs that? Hmmmmmm. While the framers finished the roof, Bill worked on his next PITA job – installing the weather-stripping. Bill did say it wasn’t that bad of a job.

Bill showing off his work.

Bill showing off his work.

Weather stripping close up

Weather stripping close up

Thursday, Nov. 14, the framers installed our windows. Those went in really quick.

Windows going in

Windows going in

West wall

West wall

Close up of triple window in front bedroom

Close up of triple window in front bedroom

Rear of home

Rear of home

Preparing for the triple garage window

Preparing for the triple garage window

We had to go over with Greg (the framer) the height we wanted our vault to go in the family room and bedroom. Greg put up a board in the master bedroom to get my approval. The height on the flat center turned out to be about 10-1/2 ft high. Perfect! The vault would go up 18 inches from the 9 foot ceiling.

Board where the flat part of the vaulted ceiling would go in the master bedroom.

Board where the flat part of the vaulted ceiling would go in the master bedroom.

And, this is what the shape will look like. Imagine drywall up there. We wanted some extra height in the master bedroom as we have a large wooden canopy king bed going in there without it feeling dwarfed. Time will tell!

Master Bedroom vaulted ceiling with flat center

Master Bedroom vaulted ceiling with flat center

The other things on the framer’s list to complete on Thursday was the Family Room ceiling, the master walk-in shower bench, and building the fireplace structure.

Family Room vaulted ceiling

Family Room vaulted ceiling

The Family Room flat section goes up to about 14-1/2 feet.

Master bathroom shower bench

Master bathroom shower bench

This is my favorite photo of the unfinished house so far. It’s the fireplace flanked by two eventual window seats and the vaulted with flat ceiling. I can’t wait to see how this will turn out cause I already like the shape it’s taking on.

Fireplace structure

Fireplace structure

Friday, Nov. 15, the roofers and framers were hammering away in the very early morning.

This slideshow requires JavaScript.

Bill picked up all the excess wood that he couldn’t use and burned away.

Lots to burn

Lots to burn

By the end of Friday we had the framing and roofing completed . . . or so we thought! 😕

Saturday afternoon, Nov. 16, and Sunday, Nov. 17, Bill and I swept and vacuumed the interior of the house. We had to lay out, measure, and mark all the cabinets and appliances on the floor before the plumbers and HVAC guys came on Monday morning. It was a lot of work but also exciting to see if everything would fit the way we thought it should. Bill had built our cabinets prior to the house being framed, so we had to make sure everything was going to fit!

Looking from the family room toward the kitchen

Looking from the family room toward the kitchen

Looking from the family room toward the dining area on the left and kitchen to the right

Looking from the family room toward the dining area on the left and kitchen to the right

Looking toward the front door

Looking toward the front door

Looking from the family room to the hall closet on the right of the entryway

Looking from the family room to the hall closet on the right of the entryway

Looking through the wall that separates the family room and the master bedroom

Looking through the wall that separates the family room and the master bedroom

Let me back up a little here. Thursday, Rick from Lensing (where we are getting our bathroom vanities/cabinetry) came to measure. The framing wasn’t all complete (one of the walls for the window seat wasn’t done yet), but he came anyway. I wasn’t there. He told Bill that in our hall bath we would have to go with 18 inch depth cabinetry as there was not enough room for the 22 inch for which we had originally planned. 😯 Bill and I re-measured the bathroom during the weekend to see if it was framed correctly. We came up with the same measurements that were on our plan. How could this have happened? We knew the bathroom was going to be tight but I had 22 inch deep vanities in my 3D software and they fit and Jim had 22 inch standard vanities in his drawings. Something was off. The master bedroom closet was right behind this bathroom. I was willing to give up three to four inches if that wall could be moved. But, looking up, it appeared that the ceiling joists were laying right on the top of that wall. We figured it could not be moved without a lot of difficulty. Crud!

I didn’t know what to do. I really didn’t want 18 inch deep cabinets. Jill said maybe we could go with a standalone furniture-like vanity if they came in that depth. Jill said she would talk to Jim and have him look at the bathroom and see if he could see what options we might have. In the meantime, Bill and I went out to Lowe’s Saturday evening and looked at 18 inch depth cabinets. There weren’t many but I thought if that is what we had to do, then that would be what we would have built. However, I would have to get rid of the full-size cabinet next to the vanity. It would close in the bathroom too much.

Sunday, Jim walked through the house to see if everything was framed correctly. Jim, Sr. came over and we gave him his first tour of the house. Jim, Sr. made a comment that our beam that separates the kitchen/dining area from the family room was one big beam! And, I kept looking up at all that space up there, saying that I guess we should have thought about that space before. You could stand up in that space. I verbalized to both Jims and Bill that maybe we should have put a room up there. I had mentioned the space to Jill earlier, too. Even if we gave up part of the laundry room to build a staircase up there, she asked if I would really want to go up there without a window? Jim said if we wanted to do something with the space, now was the time. My head was spinning.

Should we make attic into a bonus room?

Should we make attic into a bonus room?

Jim and Bill climbed up the attic stairs and walked up in the area above the kitchen and laundry. Jim finally said, yes there would be enough room to make about a 14×14 room with slanted walls. He then asked if we wanted to spend about $15-20K to make it happen. And, I still wouldn’t have a window! Finally, I said, it’s not worth it. I also said that soon the drywall would be up and I wouldn’t look up at it and wonder. Besides, Bill and I said . . . this house would have no stairs. And, I wasn’t willing to give up my laundry room.

Once that was decided, we moved along. We had to see about that hall bathroom. The guys got to re-measuring the room and found that it was framed correctly. However, Jim discovered that the bathroom door had been placed in the wrong place. Jim said we had a couple of options. If we wanted to leave the door where it was and move the wall back into part of the closet space, we would have to check with the framer to see if the wall could be moved. Or, the easier thing would be to check with the plumber to see how deep the tub enclosure was going to be so we would know how many inches to have the framers move the door over. Bill decided to check with the plumber the next day.

Jim, Sr. said we really needed more support for that big old beam by the entry door from the garage. He said we didn’t want it to eventually sag. Bill discovered that the wall to divide the dining area from the family room was only 10 inches and it was supposed to be 2 ft 2 inches. Jim looked at the fireplace structure and asked Bill why the one support was so high up and then when Bill got out the instructions, they discovered a section had not been built. Bill said he would call Greg the framer later in the week to update him once we knew what we were going to do in that bathroom. Honestly, we decided that if these were the only things that were wrong in the whole house, we were in good shape. The framers had done an awesome job and we were pleased. And, Greg had told us he would be working close by and would come back and install the exterior doors as soon as they came in. These extras could be a “rainy day” for them.

Monday, Nov. 18, the plumbers and the HVAC guy came. The HVAC left aluminum pieces to where he thought vents should go. Bill and I had to go through the house and move the vents to where we wanted them to be installed when they came back. Thank goodness I had already placed my furniture in our 3D house planning software so I knew where I could move the vents.

Vent in the entry way

Vent in the entry way

Vent in the front bedroom

Vent in the front bedroom

I told Bill I wanted the vents by the window seats to be installed in the toe-kick of the window seats. Bill had never seen that before. I showed him this picture and said that is what I wanted. He will tell the HVAC guys when they return Monday, the 25th.

Vents in the window seat toe-kick

Vents in the window seat toe-kick

The plumbers did all their rough-in work last week. And, they installed the tub enclosure in the hall bath. Turned out the tub enclosure was an inch deeper than we thought it would be. Which made things even more challenging. If we moved the bathroom door, it would only give us an extra inch. Things weren’t working in our favor. So, we decided to make the bathroom door a 28 inch door instead of a 30 inch door. Our master bathroom door is 36 inches. That’s the one that is most important. The bathroom we are using in Jill’s bonus area has a 28 inch door and it works fine for us. So, by going with a smaller door and probably use a slightly less wide trim inside the bathroom, we can have a 20 inch deep vanity. I called the granite place to make sure the sink we purchased will fit with the smaller depth cabinet. It will. Whew! In addition to the tub enclosure being deeper, the framer was going to have to either move the wall back from the adjoining linen closet (so we had a wall to attach drywall) or make a fake wall right behind it. Again, we saw problems with moving the closet wall because it was supporting ceiling joists.  Here’s what we changed the cabinets in the hall bath to look like:

Hall bath cabinetry

Hall bath cabinetry

Here are photos of the plumbing work.

This slideshow requires JavaScript.

The well guys came back out this past week, too, and trenched and installed pipe from the well to the house. The framers ended up coming back out and fixed all our tweaks and did it in two hours. And, they installed our exterior laundry room door, too! Yay, Framers!!!!

Laundry room exterior door installed

Laundry room exterior door installed

Extra support for the big old beam

Extra support for the big old beam

Door frame changed in hall bath

Door frame changed in hall bath

Installed a fake wall behind the linen closet wall so they could hang drywall.

Installed a fake wall behind the linen closet wall so they could hang drywall.

Extended the window seat dividing wall to 2 ft 2 in

Extended the window seat dividing wall to 2 ft 2 in

Built the extra frame for the fireplace. It will be added to the structure after the fireplace is installed

Built the extra frame for the fireplace. It will be added to the structure after the fireplace is installed

Yesterday, I ended up sweeping up all the piles the plumbers left throughout the house like below.

Piles left by the plumbers

Piles left by the plumbers

Monday the HVAC guys are supposed to be back to make any exterior openings they need to do. Because either Monday or Tuesday, the Hardie Board siding is being installed. Monday, I have Rick from Lensing coming back to do final measuring for the bathrooms and window seats so we can place the order. We’ve decided to go with the brandywine finish for the cabinets as it matches the mahogany Bill is using for the kitchen cabinets.

The front door and the fireplace both got delayed. They were supposed to be installed this past week, but now both will supposedly be installed the week after Thanksgiving.

I’ve spent some time looking at materials for the kitchen backsplash. We are getting closer to making that decision. I’m leaning toward glossy tan subway tiles. We also got our granite samples and they match real well with the cabinets and tile we picked out for the two bathrooms. And, I had to purchase another two light fixtures. I wanted to have a light for each of the window seats. I order two more of the same sconces I had already purchased. Two will be in the interior of the entry way and the other two will be in the window seats.

Entry Sconces and Window Seat Sconces

Entry Sconces and Window Seat Sconces

And, I’m thinking I may just change the spot for the exercise bikes in the laundry room to my computer area. 😆 I’ll probably be on the computer way more than I’ll be on that bike. And, the view is so nice and I’d have my own space.

Future computer area

Future computer area

We are taking each day as it comes and doing what we can to make decisions and adjustments. So far it’s all been GOOD!

They Nailed It!

Measure twice, cut once. ~English Proverb

This blog post is going to be chocked full of photos. The framing crew did an amazing job since I last posted. Friday, November 1, they concentrated on sub-floor installation.

First floor board down!

First floor board down!

Ready to place down the board.

Ready to place down the board.

My view from the pole barn

My view from the pole barn

Making sure everything is plumb

Making sure everything is plumb

Lots of floor boards

Lots of floor boards

Everybody has a job

Everybody has a job

Here’s what it looked like at the end of Friday, November 1. All of the sub-floors installed except a small area in one of the front bedrooms. I enjoyed walking on the flooring the next day. The floor plan was beginning to take shape. I could start seeing where different rooms would be located.

IMG_0910

Looking from the front to the back of the house where you would enter from the garage.

IMG_0913

Looking from the family room area toward two front bedrooms

View from the west end looking east

View from the west end looking east

The framers glue and nail the floor boards. If you really want to take another step in making sure your floors don’t sag or hardwood floors squeak, you should screw the floor boards. Bill wanted that extra step. When Jill and Jim built their home, they had the construction crew screw the floors after the framers were done. There are no members of the construction crew any longer. If we want extras done, we either pay someone to do it or do it ourselves. Well, not “us.” It’s always Bill. Here was another PITA job.

Bill talked with Greg the framer about screwing the floor boards and Greg said he had a screw gun that Bill could use.

Screw gun

Screw gun

Bill ordered the screws from the lumber company and they delivered them the next time they came out.

Screws

Screws

In between his shared General Contractor job, Bill worked on cabinets. He put the drawers together to make sure they all fit.

Kitchen cabinet drawers

Kitchen cabinet drawers

Drawers joined together without bottoms

Drawers joined together without bottoms

Monday was the day I was looking forward to watching the framers. It was the day that walls would be built. I decided to spend the day down at the pole barn watching. I was so excited! Since we had the time change early Sunday morning, the framing crew told Bill they would be ready to work EARLY! He went down to the pole barn at 6:00 am to open it up and get out any of their supplies he was storing for them. Bill said it would be awhile before they would work on any walls as they needed to finished the floors first. I told Bill to text me when he thought the walls would start going up.

At 9:00 am, Bill sent me this pic via text and it said – Walls!!!

IMG_2805Here’s the funny about this. I didn’t see or read the text before I went down to the pole barn shortly after 9:00 am. Bill came walking out smiling from ear to ear and asked, “Did the text get you down here quickly?” I said, “What text?” I looked at my phone and saw the text and the pic and noticed that there were no walls up on our house. Then Bill said the pic was from when Jill and Jim were building their house three years ago! He thought it would be a funny joke to play on me thinking I would have missed seeing all these wall going up. I guess it would have been a mean joke if it had worked! 🙄

It was a cold morning but Bill let me use the heater because we had the garage doors open. I loved watching the framers from my chair in the pole barn. Here are some pics of how the first couple of walls went up. The framers would measure and cut and then nail the structures together while they were flat on the floor. Then they would lift the walls and nail them in place. Then they would nail another 2×6 to something else to make sure the wall didn’t fall.

This slideshow requires JavaScript.

Here is a set of photos showing the master bedroom and master bath walls going up.

The guys worked on several more walls on the floors but nothing was going up. Bill decided to go up to the house and eat lunch. I decided to stay and watch as the guys worked. Bill came back around 1:00 pm just in time to see this:

That was impressive! It took all five members of the crew to lift that wall. It was the family room wall with the two windows flanking the fireplace, then the dining room with door, then the laundry room wall with door.

The guys worked together to get it totally squared and in place. Greg was at one end and was calling down to the guy at the other end. He asked, “How is your end?” The guy said, “It’s almost perfect.” Greg said, “What do you mean almost perfect? Do you think Mr. Rogers wants to install his almost perfect cabinets on an almost perfect wall?” Everyone laughed. I like Greg.

After they nailed the wall in place and I had time to sit and look at the wall, I noticed that something was wrong! 😯 I called Bill over and said, “Honey, there is a window missing in the laundry room next to the door.” He looked at me and said, “Are you sure?” I said, “Yep. Let me show you on the plans.” I told Bill I know the floor plan backwards and forwards.

Missing WindowBill went to talk with Greg to tell him about the missing window. They both looked at the floor plans Greg had and said he’d get that fixed. Shortly afterwards, some of the 2×6’s were removed.

Where the missing window would be installed

Where the missing window would be installed

While Bill and Greg were looking at the floor plans, Bill noticed that Greg didn’t have the correct measurements for the fireplace. That was along the same wall. They talked about a solution of how to fix the windows on each side of the wall that was already up. Greg said if he extended the fireplace a few more inches which was needed and he left the windows where they were they would not be symmetrical in placement to the fireplace. Bill had me come over and discuss if it would bother me or not about the windows. It was going to be 1-1/2 to 2 inch difference of showing drywall on one side. Bill said it wouldn’t bother him. I said I guess it was too little a difference to bother me. However the next day we talked with Greg again about the situation because the more I thought about it, the more I knew it would bug me. He said he’d re-do that part of the wall and make the window placement symmetrical. Thank you, Greg!

By the end of Monday, all the exterior walls were installed and some of the interior walls were up.

This slideshow requires JavaScript.

Bill decided to start screwing the sub-floor that evening.

IMG_2714

Bill using the screw gun

The framers were able to work a full day on Tuesday, a couple of hours on Wednesday morning before being rained out, and full days on Thursday and Friday. It is so much fun walking through the rooms that only a couple of days before were only on flat paper. Here are pics of the everything built by the end of Friday, November 8.

This slideshow requires JavaScript.

Greg thought they would be done framing by Wednesday, the 13th. Bill has called the plumber, HVAC guy, and roofer as they are next to come in. And, Bill continues to work on those cabinet drawers. As Bill always says, you can’t have enough clamps. To keep these big drawers square as the glue was drying, Bill had to use 12 clamps just on this one drawer. 🙂

One big drawer glued up

One big drawer glued up

I spent a lot of this weekend measuring the walls and rooms in the house to make sure everything was good. Especially the walls where Bill had built cabinets. These guys are great. If there was any difference (which there was only in a few places) the measurement difference was only off about 1/4 to 1/2 inch. Almost everything was spot on.

By the way, Bill did finish getting all the floors screwed. Another PITA job done!

Can’t wait to see how the house looks once all the gables and roof are on. What a difference a week made!

“Wood” You Please Build My House!

All things come to him who waits. ~Woodrow Wilson

Monday, October 28, early morning, Bill’s phone rings. It’s Jim, Sr. He says that the trusses were being delivered and Bill better get down there. It really is nice having neighbors close by who look out for you. 🙂 Bill rushed to change clothes and drove down to the site. Only to find that they had already left. But, they left us these!

Trusses

Trusses

Trusses

Trusses

For our house plan, our framer only uses trusses over the garage area. Thank goodness the delivery person dropped the trusses off next to the garage. The framer will bring in a crane to lift the trusses when he gets to that point in framing.

I came down shortly after the truss delivery to check out our first lumber delivery. I was excited! Bill said this was the first big smile on my face since we started this house-building project! 😆

Happy Sandy!

Happy Sandy!

I went back up to our apartment while Bill worked on making more wood for cabinets. Unfortunately, Sunday when he was making dovetails, he had an epic fail. 😥 Something went wrong with the dovetail jig or some piece of equipment and it apparently was slipping a little at a time without him knowing it. Pros: Bill has lots of practice pieces of drawer wood, lots of wood chips for the chickens, and lots of kindling. Cons: Bill had to make more wood and lost a day’s work.

I text Bill two hours later (10:00 am) to see if any more lumber had been delivered. He answered, “No!” I text again at noon and got the same reply. I asked if he should call Chuck at Kight Lumber. He text back a few minutes later and said that Chuck said lumber was on the way. So, I went down and waited and waited and waited. I enjoyed the sunshine and walked around the site dreaming how it would look in the next couple of months.

Bill came to a stopping point at making wood and decided to drive back up to the house to eat lunch. I stayed down at the pole barn. It was 1:30 pm. No sooner had Bill got up the driveway to Jill & Jim’s house, the truck pulled into our driveway and backed into the area in front of our house. I called Bill to tell him to come back down.

Lumber delivery truck

Lumber delivery truck

The guy started to unload a bunch of boxes and put them on the garage concrete.

IMG_2588IMG_2589

Nails

Nails

IMG_2591

Silver rolls are termite shield

Stainless steel rolls are termite shield

Sill plate sealer

Blue foam rolls – sill plate sealer

Closer up of lumber truck which had 2X6’s for exterior walls and insulation boards (blue boards).

Lumber truck

Lumber truck

The delivery guy and Bill discussed where to unload the lumber and Bill suggested behind the house. So he moved the truck. I kept wondering how he was going to get all that lumber off the truck. We soon found out. Talk about “dropping off a load of lumber!”

If you watch the video you will hear me say, “hmmmm!” after those blue insulation boards fell off sideways! 😯 Thank goodness they were all okay.

Bill checked on the lumber afterwards and all was fine. The lumber company also sent a box of heavy-duty plastic to cover the wood since we had a large weather system heading our way. Before leaving, the delivery guy covered the load of lumber.

Bill checking the lumber that was dropped off

Bill checking the lumber that was dropped off

Just a little chipped up, but not enough to hurt anything

Just a little chipped up, but not enough to hurt anything

Covering the lumber

Covering the lumber

All covered up

All covered up

Bill and I decided to cover the trusses and the boxes of supplies after the delivery guy left so nothing would get wet. Later in the afternoon the rest of the lumber was delivered. And those delivery guys covered that lumber, too.

More lumber trucks

More lumber trucks

Jim talked with the framer on Monday and he said he wouldn’t be able to start until Wednesday. Bill didn’t tell me that until Tuesday morning. He knew I would be disappointed. And, of course, I was. 😦 They were predicting rain for Wednesday and Thursday, so I told myself that the framer would probably start on Friday when it was supposed to be nice and sunny.

Tuesday, Chuck from Kight Lumber came out to check and make sure they had delivered everything. He and Bill went through the list and then looked at the house plans. I was at water aerobics and grocery shopping when all of this was going on. From what I gather, there was discussion about beams – how many, how long, where they were going, etc. Bill and Jim and Chuck work through this. A 28ft beam was delivered sometime Tuesday.

Tuesday evening Jim came up to the apartment to discuss “the beam” which we were installing between the family room and kitchen/dining area.

Beam on floor plan

Beam on floor plan

He said we had to decide how far down we wanted to install the beam so he could tell the framer in the morning. And, he said that the decision would be based on how high our trim for windows and doors was and where we were installing the headband throughout the house in each room. OMG! Bill and I looked at him with blank stares! 😯 We didn’t know how to answer him. Bill said he didn’t understand it all and even though I thought I understood part of it, I didn’t know the answers to tell Jim. Jim asked us to come downstairs and he’d show us what he was talking about using their beam as an example.

What Jill and Jim's beam looks like

What Jill and Jim’s beam looks like

Jim said we had to decide how far to place the beam and then decide how much decorative trim (what you see in their beam above) we wanted to use that would come down to the height of the finished beam. As I’ve said before, we say our house is a mini Jim and Jill house as far as our interior trim. However, we do have a different trim for the top of our windows and doors. This is what ours will look like.

Trim Casings, Stool and Apron

Trim Casings, Stool and Apron

We said to Jim that we want our finished beam to come to the same height as theirs. Our frame was a slightly different size than J&J’s but Bill and Jim determined where the beam would hang. Jim wanted that information by the time he met with our framer at 7:30 the next morning on our property. Jim gave us some homework to do making sure we had the headband figured out in each area and that it would work at the same height we had chosen in the kitchen/dining/family room (at 8 ft). We decided on the headband height at 8 ft based on the fact that we have soffits in the dining area that come down to 8 ft. This was tricky business.

The beam had to be decided before the framer framed that section. So, that part was decided. However, Jim gave us some homework. He wanted us to look through our house plans and see if the headband worked at 8 ft throughout all the other rooms. Also, he said to think about if we wanted any more beams or decorative drop downs anywhere in the house. Here is an example of what Jill and Jim did in their hallway and entry into hall.

Drop down decorative dividers

Drop down decorative dividers

Here is a picture of how the headband works in J&J’s kitchen.

Beam and headband

Beam and headband

How headband circles around every room

How headband circles around every room

Jill and I are huge fans of architect Sarah Susanka. I think I own all of her Not So Big books. I LOVE her Home by Design book. She explains how you can break up or designate areas of your home just by using trim or drop-down ceilings. Jill and Jim used the decorative drop down trim above the opening when you transitioned from their entry to the hallway (seen in one of the photos above). Then, they used two more in the hallway. One was to designate that the area was still part of the main level living area (office and half-bath). The last one in the hall was to designate that area was another entry area from the garage (an open mud-room type entry with cubbies for coats and shoes).

Another idea that Susanka uses in her house designs for Prairie and Craftsman homes is the headband. The headband provides a connecting theme from room to room throughout the house. It can be made of different widths of wood. It is also a great way to make ceiling heights look taller. That is accomplished by painting the area above the headband a lighter color than the wall color. The ceiling is painted and finished in the same color as the section above the headband. Susanka says, “So the entire area of the room above the headband is like the lid of a box.”

So, back to our homework. The next morning Bill and I looked at our house plans. We decided we didn’t have any other areas in the house where we needed a beam as a divider. We double-checked the height of the headband in the kitchen/dining area by starting at the height of the soffits in the dining area and working our way around to the beam. The 8 ft height worked great and that would butt up to the top of the big decorative beam. The trim for the beam will be 12″ and that will bring the beam to a height of 7 foot from the floor. That was the height of J&J’s and it was perfect. Whew!

I looked through the plans and decided I thought we could add a drop-down decorative divider at the entrance to the hallway to the master bedroom suite area.

Entrance to Master Bedroom suite area

Entrance to Master Bedroom suite area

Bill and I thought we were okay as far as the headband in all the other rooms. I said I wasn’t planning on using a headband in the laundry/pantry room.

We went downstairs with our house plans and a camera. Thank goodness Jim and Jill were up and ready for work and gave us a few minutes to talk over ideas. We shared our idea about the decorative divider at the master bedroom hall and they thought that was good.

Drop down decorative trim to divide spaces

Drop down decorative trim at master bedroom hallway

Jill checked each of our rooms to make sure the headband at 8 ft would work and she said it did. She also said we could do the headband in the laundry/pantry with no problem. I may still do it. 😕 What’s a little more wood, right?

The only part I was struggling with was how to make a transition from our very wide entry (which has 9 ft ceilings) to our vaulted ceiling family room.

Entry to vaulted ceiling family room

Entry to vaulted ceiling family room

This is a wide span of 9 ft ceiling height, with a beam to the right that drops down to 7 ft. The ceiling height changes at the family room with a vaulted coffered ceiling with a flat center. I didn’t want a plain drywall opening at 9 foot. So Jill and Jim suggested we make a drop down 1 foot wall right before the dotted line designating transition from the entry to the family room (on the plans above). We will run a headband at the bottom of the wall to continue our theme. It will look like the entry wall from J&J’s hallway to their two-story family room. The exception will be our wall will be almost 18 feet wide!

Drop down wall from entry foyer to family room

Drop down wall from entry foyer to family room

Once all of that was decided, I took pictures of everything so we could use for the framer and trim carpenter. Bill asked that I print out the pictures so he could keep them down at the pole barn where he had a table designated for house plans, specification document, and photos.

Jim took the kids to school and came back to meet with the framer. Bill got everything together and headed down to the site. The good news was that the weather held off on Wednesday, temps got up to 75 degrees, and the framing crew got in a full day’s work. Here are pictures of what they accomplished the first day.

Installing insulation board

Installing insulation board

Installing the sill plate

Installing the sill plate

IMG_0884See the 28 ft beam in the photo below? There is only a part of it in the photo. It’s covered in plastic.

IMG_0885

Floor joists going in

Floor joists going in

More floor joists laid out to nail

More floor joists laid out to nail

Day 1 completion

Day 1 completion

Day 1

End of Day 1

Floor joists done!

Floor joists done!

Bill has been working on the cabinets in-between helping out with the contractors. He got the dovetails working again.

Cabinet drawers dovetailed

Cabinet drawers dovetailed

Beautiful dovetail work!

Beautiful dovetail work!

Drawer without a bottom

Drawer without a bottom

One big 'ol drawer made

One big ‘ol drawer made

We had a washout today because of the weather. Here was our radar earlier this morning. Hasn’t gotten better.

Today's weather

Today’s weather

Can’t wait until I see some vertical boards going up tomorrow. Framer said the house would probably take 1-1/2 weeks to complete. I hope the weather holds up!

And so we begin!

The way to get started is to quit talking and begin doing. ~Walt Disney

We hit the ground running after I posted on Saturday morning. I went down to help Bill while he staked off a huge section of the front yard so no one would drive on it. Basically, I only held the stake straight until Bill pounded it down into the ground.

Stake Pounding

Stake Pounding

Yard staked out

Yard staked out

Then, I got called off the survey staking committee and Jill put me on chauffeur duty to pick up Jack from a Boys Scout event. It takes a village to do all the work on the compound. 🙂 Joan took Megan shopping at the school’s marketplace and shopping for birthday ideas. Jill cleaned house.  Jim, Jim, Sr., and Bill did the staking for the house. We had to get everything done before Jack’s 2:30 football game.

Not sure if you can see or not, but there are red survey flags in those piles of mud. The flags mark the four outer corners of the house so the foundation guys can pour the footers in the right place.

Survey flags

Survey flags

IMG_2285

IMG_2284

Sunday Bill went shopping to buy all the electrical components to hook up his cabinet making equipment to a generator. He had tested starting the different pieces of equipment with the generator. Some had better results than others. But, everything eventually started and it seems that he will be able to run his equipment off the generator since we have no electricity in the pole barn yet. Bill’s pole barn “open house” has been delayed a week because of his construction duties. However, Bill has made great strides in getting the workshop almost ready for duty. He would only let me take a couple of photos until he has his open house. Wonder if he’s going to serve refreshments? 😉

Back workbench with raw mahogany wood stored above

Back workbench with raw mahogany wood stored above

Sunday, I spent a lot of time measuring Jill’s fireplace and windows again. Unfortunately, when Bill and I discussed the window seats on each side of the fireplace and window and window seat measurements, we discovered we needed to make our fireplace larger than was drawn on our house plans! 😯 The fireplace and windows are gonna be the death of me yet! I was dreading breaking the news to Jim that we needed to make more changes. However, it is better to find out these mistakes before we start framing and before we order the windows. And, Bill and I looked again about how we would extend the fireplace stone up to the ceiling and it just wasn’t going to work either. Grrrr.

We had a construction meeting with Jim on Sunday evening (Sept. 22). He gave us a lot of homework to do on Monday. The three of us each had our to-do lists.

  • Jim worked with our vendor for Hardiboard siding and trim; updated house plans; made phone calls and arranged for permits; and lots of other behind the scene things he does – like discover that our bid for trusses was not for attic trusses.
  • Bill arranged for a porta potty and dumpster; called another company to compare block prices; called vendor we planned to use for block material and had them resubmit their bid with updated information and arranged for them to deliver block on Wednesday; called another roofing material vendor and inquired about pricing; both of us visited vendor and picked out shingles and got a quote; called lumber company and had them resubmit their bid with attic trusses; ordered sand; and called Vectren to ask about electricity and gas hookups; cut our grass; moved the trailer to the side of the pole barn; arranged a hose hookup from Jim, Sr’s water-spout down by the lake; and found spots where the porta potty and dumpster could be stored during construction. Whew! He was a busy guy.
  • I had to re-work all our windows and re-design our fireplace. I also had my household chores of 5 loads of laundry, unloaded and loaded dishwasher, picked up kids from bus stop, wrapped Megan’s birthday gift, took Jack to football practice, and helped Jill prepare Megan’s birthday dinner.
Jim, Bill and I shared lots of phone calls that day. Jim found out that the Health Department said we needed to add more soil over the area where we were having the septic installed. Saturday when we were talking with our septic installer (same guy who did our excavation for pole barn and our driveway and who will also be doing our final grading), he said he could get top soil for a cheap price per dump truck if we’d like it. Bill wanted to get a couple of loads for grading and had made arrangements for him to bring that on Monday. Well, when we found out we needed more soil for the front area, Jim told him to just bring it, too. I think we ended up with two loads in the back and four loads in the front. It’s really nice soil.
Top soil for final grading

Top soil for final grading

Soil for covering the septic area

Soil for covering the septic area

While I was re-working the window schedule, I asked Bill if he thought our windows for the front bedrooms would be down too low. We measured everything again! I called the window guy and asked him what the next size window height down would be. We would have to go down from 56″ to 48″ in height. Where I loved the taller windows, I really wanted the tops of the windows and the doors to match across the exterior of the house. But, if I wanted to keep the 56″ height and still have them higher from the floor board, I would have to raise the top height. Again, Bill went outside to measure where that would take our windows. It ended up they would be up so high that they would be one board down from our trim board. That just wasn’t gonna look right. I ended up using our Home Architect 3D software again and changed all the window sizes to get a better look. Bill and I made the decision to go with 48″ heights in the bedrooms and in the laundry room. We left the two window seats at 56″ because those windows will be lower to the floor. Of course, then I had to call the window guy back and ask him to give us a new quote. Brother!

I played with the fireplace and came up with a new design. Here’s what it might look like.

Fireplace with border

Fireplace with border

Early Tuesday morning Bill went down to the pole barn – what is now being called our construction headquarters. The first thing to arrive was important. 😀

Porta Potty!

Porta Potty!

By the time I left to go to water aerobics around 10:15, this guy was running this bobcat back and forth trying to smooth out the area where the footers would be dug and poured.

Bob cat busy

Bobcat busy

It wasn’t long and the dumpster guy came to assess the area for the dumpster. Bill decided to put it to the right of the turnaround rock in pic below. The guy said it should be delivered sometime this week.

IMG_2295

I ran errands after water aerobics (even got my flu shot) and got home just in time to pick up the grandkids from the bus stop. Jill and Jim’s yard to the west of their driveway was lined with trucks and there was a wheeled digger with a backhoe digging those trenches for the footers.

Wheeled digger with backhoe

Wheeled digger with backhoe

While I was parked at the end of the driveway waiting for the bus, some guy drove his car into the grass to the east of where I was sitting and sped around me and parked off the driveway near the construction. He slowly got out of his car and I noticed he was a big guy. Didn’t look like he was part of the construction crew to me. I mentioned him to Jim and Bill that evening and they weren’t sure who he was. It turns out he was probably the county concrete footing inspector cause we got an email the next day that he had been out and approved it. Yay!

Bill held down the fort at the construction site and I took the grandkids up to the house. The foundation crew worked until about 5:00-5:30. Here are some photos of the afternoon adventures.

This slideshow requires JavaScript.

Wednesday I went to bible study and ran more errands. Since we live out a ways, we try to combine our trips into town. Jill warned us that our gas bill would go up and it has! So, while I was gone, Bill had another busy day at the construction site. First up was the mortar sand delivery for the block installers.

Sand delivery

Sand delivery

On Monday Bill had called the plumber to see if he needed to come out before the block guys came. So, he came Wednesday morning. We had one plumber do the radiant heat and the rough-in for the half-bath in the pole barn. We were using another plumber for the house and the completion of the pole barn stuff. It appears that the first plumber may not have roughed-in the half-bath the way the second plumber would have liked it. 😳 We hope he can come up with a remedy. What we do know is that we cannot use the toilet that Jim’s parents were giving us. And, there’s something about a grinder pump thing-a-ma-jig. The plumber also put some pipes down to approximate areas where he would need plumbing access. Bill said the block guys would put them in the proper place.

Vectren came out in the early afternoon to assess the situation for temporary and permanent electrical service. The gas guy called Bill earlier in the day and said instead of him coming out, he would just get with the electric guy afterwards. Bill talked to him about transformers and whether we need one now or later. We will need a new one on the pole at the end of our driveway. They talked about if we wanted temporary electric we could run it from Jim & Jill’s transformer at the end of their driveway. But, they would have to go up 18 feet for the wires to be pulled over and Bill said that wouldn’t work with the large trucks coming in and out. If we put a transformer on our pole now, it would be a 200 amp one. However, since the house will be 400 amp, we’d have to have another transformer installed when the permanent service was needed. The Vectren guy told Bill he needed to call Vectren marketing and get a price for what the transformers might cost. We also will need to fill out a form with a checklist of any possible equipment in the house and pole barn that we might be running in the future. They have some sort of 3-year deal where they assess what revenue will be generated on what you will use and that is what they base the cost of how much we’ll pay for the transformer. Sounds complicated to me! 🙄 Anyway, the Vectren guy left Bill a voice-mail message late yesterday that they could get us temporary electrical service by January 2014! 😯 That’s not gonna work. Bill will be calling the Vectren guy back today.

The block delivery arrived around 2:00.

Block delivery

Block delivery

Heavy crane to lift the block

Heavy crane to lift the block

Today someone from the foundation crew will be back to remove all the ground around the footers to make the ground level with the footers. You can see from the pic below what I’m talking about.

Ground to be leveled

Ground to be leveled

The block installers are scheduled to arrive Friday to install our block.

When Jim started to call subs over the weekend to schedule them he found out our framer would not be available for another 3 weeks! He checked on our second choice framer and he was 4-5 weeks out from being available. So, we are going to wait for our first choice guy. Actually, I’m kind of glad we will have a delay because I’m taking a trip and I don’t want to miss the framing of our house. I want a front-row seat. Don’t get me wrong, the footers and block are exciting! However, I think the framing is the best part in the beginning. It finally brings all these months and years of planning from a flat or 3D rendering to an actual structure that we can stand in and walk through.

It is Bill’s hope that he will be able to start working on cabinets in the next two weeks.

Until then . . .

One journey ended . . . Another to begin

A bank is a place that will lend you money if you can prove that you don’t need it. ~Bob Hope

I am happy to say we FINALLY closed on our construction loan Thursday afternoon (Sept. 19)! The process took longer and was more strenuous than we ever thought possible. We started our first loan application on June 17!!! And, if you really want to count the whole process, we actually started a preliminary pre-approval type process back in January with the regional loan officer in the Indy area. Needless to say . . . that was a journey we are glad has come to a close.

Sherry, our loan originator, continually told us she didn’t see any reason we wouldn’t be approved for the loan. But, the relentless questions and requests had us doubting that fact. This was our first construction loan – ever. We have purchased several homes and refinanced many times as the rates got lower and lower over the years. The construction loan process was a whole other beast. 😯 I’m an organized person, keep receipts, capable to create spreadsheets, scan documents and save them in pdf format, and attach them to emails. Boy, did those skills come in handy over and over again.

We eventually found out why we were experiencing so many questions and requests. Apparently, the bank had never dealt with someone who had purchased so many items for the house or who had already paid for improvements to the land (well, pole barn, driveway, etc.) prior to getting a construction loan. 🙄 We only mentioned all of items when we initially started the loan process because we thought it could be used toward our equity for the loan. We really didn’t need most of it for that. It would have been a lot easier if we had purchased the stuff out-of-pocket after we had the construction loan. Purchasing it before, everything had to be documented and recorded for HUD. The appraisal came in fine.

At one point, Bill said he’d just take the money out our investments and pay cash for the rest of house construction.  However, our financial adviser said he could make us more money than the 4% interest we will pay for a construction/mortgage. And, since we can still deduct the interest on our taxes and we can afford to pay for the mortgage in retirement, we went this route. Hopefully, we won’t regret this. 😕

Enough about that nightmare issue.

To lighten the mood and has nothing to do with construction loans or building a house, here is pix of some wildlife we see out where we live. Just moseying down the road – a family of turkeys. They wouldn’t get off the road either until I finally drove closer to them. The Dad (on the left) finally walked to the right of the road to join the Mom who was up in the bush area. The three youngsters finally flew toward the left. You can see my speedometer hologram in the windshield set at 0. I was parked while taking pictures. 🙂

Turkeys!

Turkeys!

Now, for the exciting news!!

drum-roll

We are finally going to start building our house next week!

As soon as we knew we got the appraisal and knew we were going to close on the loan, Jim said we needed to make any changes to our house plans and spec document ASAP. He needed to send the plans and specs to the building commissioner to pull our permits and the foundation contractor so he could start as soon as we had the permits. It was also time for final decisions. Once the footers are poured, no more changes to the house plans! Jim and Jill both asked if we were ready to move forward, because we were getting ready to spend some big money really soon! And, no backing out of the process. We both said . . . “Bring it on! We are ready! More than ready!”

I went through the plans and specs and marked them up with any changes we might have had since getting bids back and contracts from subs. While I was doing that, Bill spent his time going through contracts, cleaning up our construction binder, and putting all the information into Microsoft Project. Bill had downloaded a house construction template and had to tweak it to fit our construction. We are using MS Project as a scheduler. We spent two long days (Tuesday & Wednesday) working through all the information and updating everything on the digital versions. We sat down with Jim late Wednesday evening to go over all the changes.

Bill and I spent Thursday morning making more changes and finalizing the spec document so we could email to Jim. Jim made all the changes to our plans and emailed off the documents to the building commissioner and foundation guy. One of our changes we had to make was to our fireplace. We originally wanted our fireplace to look like this:

Fireplace we like

Fireplace we like

After Jim drew the fireplace for us to figure out sizes, we discovered the columns would have to be skinnier than the ones in the picture. Then we noticed that we would not have any room on the hearth to place our fireplace tools or to set wood down on the sides of the fireplace doors. So, without a fuss, I said I’d give up this dream. With the modifications, it would change the look of what I had envisioned. However, that meant we had to come up with a new design and fairly quick. I found this design:

Screen Shot 2013-09-19 at 6.24.20 AM

Bill liked the double wooden mantel. I did not like above the mantel. So, Bill suggested that we extend the stone up to the vaulted flat ceiling – about 13 ft from the floor. So, I did a little magic with the photo in some of my computer software and came up with something like this:

New fireplace

Fireplace with Ledge stone

Every change constitutes either phone calls, emails, or visits back to contractors. This involved our stone guy. Before we headed to our closing, we made a visit to see Rick at Tri-State Stone. The stone on this fireplace was a ledge stone. We liked that stone on the fireplace, but we weren’t sure if there was enough variation in the stone sizes like the Cutface Suede we had picked out for our exterior.

Centurion Cutface Suede Stone

Centurion Cutface Suede Stone

I looked through a bunch of photos on Houzz.com and Google and neither Bill or I liked the Cutface on that big of a fireplace. Here we go again! More changes. 😡

Rick showed us several samples of stone and several binders full of photos of buildings and fireplaces he had designed. He suggested we do a stone border around the fireplace to give it more visual appeal. Can you see the difference?

Curved border

Curved border

Square border

Square border

Of course, Bill preferred the curved one. Me, not so much. Oh, it would look great if our fireplace was curved at the top, but ours is not. And, I do like straight lines! 😉 A curved border just wouldn’t look right to me. So, I told Rick to come up with some straight lined border around the fireplace. Here is a photo of the fireplace we are buying.

Enerzone

Enerzone

We want the fireplace stone to match the exterior wainscoting stone. After looking at the Centurion Ledge we decided we wanted something else. We had picked out Centurion Cutface stone in the color Suede. Centurion Cutface has a lot of jagged edges – hence the name. I’m thinking that dust could collect a lot more on jagged edges. Bill spotted another sample of stone that he liked – Stack. It was in the color Bucks County. Hmmmm. Decisions, decisions. It never ends.

Centurion Suede Cutface Stone

Centurion Suede Cutface Stone

OR

Centurion Bucks County Stack stone

Centurion Bucks County Stack Stone

OR

Centurion Suede Stack Stone

Centurion Suede Stack Stone

I think the Bucks County’s dark stones would match the Bronze trim really well. But, I think it has too much orange color in it. I still like the Suede colors. Plus, it would go well inside and out with those burgundy color stones and the mahogany front door and mahogany cabinets and trim inside. Poor Bill. He says he has no say in colors. 😥 And, he is right. The color decisions are mine. 😀 So, it looks like we will go with the Centurion Suede Stack Stone for the exterior and fireplace. So, it might look something like this but with a straight line stone border around the fireplace:

Enerzone fireplace with Centurion Suede Stack Stone with Mahogany mantle

Enerzone fireplace with Centurion Suede Stack Stone with Mahogany mantel

Now, we just have to see if Rick has a sample of the Centurion Suede Stack stone and we’ll take back the other three samples we have. Check that off the list!

We finally got a long-awaited quote for truss over the garage lumber package from one of the lumber yards on Thursday, too. Bill spent most of Thursday afternoon and early Friday morning comparing that quote to the other one we had. Decisions had to be made which lumber yard we were going to use. When Bill picked up the quote, they handed him our window and exterior door quotes. I looked at them quickly and noticed that both of those quotes were older ones. Oh, no! We don’t want them to order the wrong things! 😯

Friday morning Bill emailed the window/door guy and told him our concerns. He asked if we could come down and meet with him and go over the quote line by line. We met with Joe on Friday mid morning. Thank goodness we did that. We found some errors on the quote – like white interior prefinish on two windows! We are supposed to have bare wood so it can be stained. Plus, Joe was great to suggest which way a window should open in each room. We double-checked everything and he made the changes and printed us a new quote and emailed Jim the revised final one. I struggled with the interior borders of the window screens. They came in white, almond or bare wood. Bill was leaning toward the Almond but I really didn’t like the color against a Mahogany color (which would be our trim color). We may live to regret the decision I finally made, but I went with bare wood and will have our painter stain it along with the window and door trim. I’m sure our painter will regret that decision, too!

The meeting with Joe was a GREAT experience! In fact, I told Jim I wished we could do that with all the major contractors to make sure the correct things were going to be ordered. It’s so much better having the expert going through the order with us line by line. It never hurts to have several people’s eyes looking at the same thing and finding mistakes. Joe said we were doing things the right way. Making all the decisions before construction started.

Friday morning Jim said he was going to go to the County Building Commissioner’s office and see if he could pick up our building permit. He had emailed our plans the night before. I was surprised that we could get a permit that quickly. I gave Jim a signed blank check that morning to pay for the permit. As soon as we had the permit, we could start building! Jim had made arrangements with our foundation guy to pour the footers on Monday, September 23! We were finally going to start building our dream house! By the way, Megan did mention that September the 23rd was her birthday and asked why would her Daddy schedule our build to start on her birthday! 🙄 I told her that all the work would probably be done while she was in school so it would not take anything away from her day. So, Happy Birthday, Megan and Birdie (my sister)! They share birthdays.

Bill had given Jim the contact information for the block suppliers, block installers, lumber company, framer, and roofer so Jim could get them scheduled. Best laid plans always seem to change. First of all, Jim found out that we couldn’t get the building permits without a drawing from the septic installer of what the septic would look like on the property. So, that sub is coming this morning to do that. He will give to Jim and Jim will email that to the Building Commissioner on Monday. Jim said he could get the permit after that was submitted. And, since we had rain all day yesterday the foundation guy said it worked better if he started on Tuesday. And, we couldn’t start that without the permit anyway. Now we are shooting for Tuesday, Sept. 24, to pour the footers. Megan’s birthday will not be spoiled by construction after all. 😉

Today Jim is staking out our property. He is a professional licensed land and survey engineer. He surveyed all our properties. This morning Bill and I will be assisting Jim in the staking by holding tape measures. I think I’ll be able to manage that. I hope! Bill is also staking off where the septic will be installed so no one will drive over that part of our property. There is something about driving over that portion with heavy machinery that is not good according to Jim. I’m not sure what it is, but I think it has to do with heavily-compacted ground affecting the effectiveness of the septic.

I’ll take pictures today. It’s a gorgeous day to get this project started!

Next up: Hopefully pictures of actual construction of our house.

Let the Building Begin!

No, this is not the beginning of a new chapter in my life; this is the beginning of a new book! That first book is already closed, ended, and tossed into the seas; this new book is newly opened, has just begun! Look, it is the first page! And it is a beautiful one!

~C. JoyBell C.

I love the quote above. It kind of explains what Bill and I have felt since we packed up all our belongings, officially became homeless, and moved to an area which will become our newly adopted retirement community.

The plan was that I would drive down to Jill and Jim’s in my car with Goldie. Bill would drive his truck with our large trailer in tow. I have no pictures of what my car and his truck and trailer looked like. Just picture in your mind that they were all overflowing with stuff – just leaving enough room for each of us to sit in the driver’s seat of our vehicles and 1/2 the back seat for Goldie. Thank goodness there was no rain in the forecast for that day because Bill had my portable office on that trailer. I had the computer and printer in my car, but Bill had our writing-table, the printer cart, and my large leather swivel chair on the trailer. We had them packed in moving blankets and tons of shrink-wrap. My trunk was full of this stuff:

Tech closet changed into Desk Supply Closet

Portable Office Stuff

Half of the back seat of my car was full of our clothes, my computer, our coffee maker, and a bin of stuff. The front seat was full of cloth bags of food and dry goods.

Bill’s truck bed and back seat were full of his tools that he didn’t send to storage. He also stuffed in anything left in the house that I couldn’t get in the car. The trailer had three coolers of frozen food and everything left in the fridge; the Dyson vacuum cleaner, brooms, and several bins full of stuff, in addition to the office furniture.

We got up early and started packing all the above into the vehicles. While Bill worked on covering the truck bed and trailer with a tarps, I did a final clean of the house. I was on the road to Jill’s before 7:00 am! Bill was staying behind to meet with the new owners at 10:00 am to hand over the keys.

I have to tell you . . . I NEVER want to do a move like this again. It was both physically and mentally exhausting. I arrived at our property really early. So early I didn’t know if Jill and Jim were even up yet. 😯 They had gone out the night before to celebrate their anniversary and the grandkids had spent the night with Jim’s parents. When I pulled into J&J’s driveway, I was greeted by these sites on our property. The Excavation had begun for the new house, driveway, and the pole barn!

This slideshow requires JavaScript.

After walking Goldie around our new place and taking pictures, I got back in the car and drove up to J&J’s house. I parked my car outside their garage and called Jill on my cell. Whew! They were up getting ready for church. When I came into their home, Jill greeted me with a hug and said, “Welcome Home!” When Jim saw me, he said, “Welcome to the Evansville area!”

I was having some mixed emotions. Part of me felt like I was here for a visit. My brain had not wrapped around the thought that we were actually going to be living here. All I knew was that I was tired. And, I wanted to sit or lay down on something soft. Spending the last three days sitting on lawn chairs and sleeping on blow-up mattresses had taken its tow on me. After Jill and Jim left for church, I made several trips back and forth to empty the inside of my car and drag our stuff up the stairs to the bonus area apartment where we would be living. I finally collapsed on the couch up in the bonus area and fell asleep for 1/2 hour. It felt great!

Jim’s mom called to invite us for a late lunch. I told her I wasn’t sure when Bill would be arriving as I had come down earlier. Turns out Bill arrived around 1:30-2:00 and we enjoyed having a great home-cooked meal even if we felt like we were prying our eyes open from lack of sleep and pure exhaustion. Jim and Jill helped us unload our vehicles and trailer. Bill and I slept very well that night!

The next couple of days I spent unpacking and finding places in our apartment to store what we had brought. We merged all the canned and dry goods into Jill’s pantry and invaded their fridge and freezer with all our stuff. I jokingly call all the rest of items that have filled the apartment cabinets and the 1/2 bath cabinet “The Store.” I told Jill before she or I would buy anything, we needed to check “the store” first. I have every kind of cleaning solution you’d want and have enough hardwood floor cleaner to last a lifetime. 😀

Anyway, within two or three days, I unpacked and found a place for everything. This is our two bedroom apartment. We love it. Who wouldn’t? Thank you Jill and Jim for letting us use your bonus area as our temporary home. Here is where we are living!

This slideshow requires JavaScript.

Jim’s dad graciously offered the boat house for Bill to store some of his tools and all our shed items. He said he could use the space but he’d have to clean it up first. Bill spent a day or two getting all that organized. Our lawn mower has found a home under the lean-to of Jim’s parents big red barn. Our new “commune” living is working out okay! 🙂

We had a family meeting with Jill and Jim one evening the first week we moved in to discuss our living arrangements. Jill is working full-time with Karama now and the family is adjusting to her busy schedule. In addition to Jim working long days, he is also handling all the stuff with our new house with the family construction company. Bill and I said we’d do whatever we could to help them while we were living here. So, Bill and I watch the kids if they are not in a summer camp so Jill can work at her new office space. I also said I would make dinners. We are trying to base our menus from the overflowing pantry and freezer first. And, I usually do laundry during the week. Bill does projects for Jim and Jill. Jim is a little shy in asking for help, but Jill always seems to have something for Bill to fix or do. 😉

On top of getting settled in, Jim sent out the bids for our new house the Tuesday we arrived with a deadline of submitting bids for Thursday, June 20th. Jim was leaving for Africa on Sunday morning, June 23. (1/2 trip was a mission trip; 1/2 trip he is doing a Mount Kilimanjaro climb) It was a busy time for all of us!

The excavator spent a couple of hours each day moving dirt around on June 11-13. Jim text us that he had a meeting scheduled with the excavator at our property the evening of June 13 and we needed to be there. We were suppose to go over decisions of elevations of the pole barn pad and the driveway and house/garage. Hmmmm, okay. I didn’t know what I could contribute, but I said I’d be there with Bill.

All I can say is we have some rich dirt on our property. It smelt like manure when we went down there that evening. I think my only contribution that evening was to ask Jim’s dad for his advice on the excavation. I liked his advice and said to go with whatever he said. Here are some pics of the excavation job and a video of the very large commercial equipment our excavator used. They had to really build up the pole barn pad. But we were very fortunate we didn’t have to haul in dirt. We had enough by digging out the driveway and part of the crawl space for the house. I loved watching that big ‘ol machine, but I was afraid it was going to tip over!

By the time we finished our first week here, Goldie and I both started having some problems. Since we had just been down here for a short time, I hadn’t found a doctor yet. (I have one now!) So, with the advice from my Indy doctor’s office, on Tuesday, June 18, I took myself to a local urgent care and ended up with a diagnosis of a bladder infection (my first). They sent me away with a prescription for an antibiotic. I took Goldie to the vet that same afternoon. They were unsure what her diagnosis was (she was having bladder accidents!) but gave her a shot and put her on an antibiotic, too! Both of us have been fine ever since we got on medication. Yay! Funny thing is, both the doctor and vet said it could have been the stress of moving.

They delivered the pole barn materials on Thursday, June 20 and started building it the next day. Here is what they did on Friday the 21st.

First day poles up

First day poles up

side view

back view

another side view

side view

They were supposed to be back on Monday, June 24, but we had storms all day long. We ended up getting 4-5 inches of rain! No building that day. Even though it was extremely muddy, the crew returned and worked every day Tuesday through Friday, June 25-28. They got that pole barn up so quickly. Here are pics of the progression:

Day 2

Day 2

End of day 2 Framing complete with windows

End of day 2 Framing complete with windows

Day 3 - the siding going on

Day 3 – the siding going on

Day 3 - white door is going to be painted bronze

Day 3 – white door to be painted bronze

Day 4 finishing the siding

Day 4 finishing the siding

Day 4 - front of barn

Day 4 – front of barn

End of day 4 - roof on, trim finished - front of barn

End of day 4 – roof on, trim finished – front of barn

Day 4 - side of barn

Day 4 – side of barn

Day 4 - back of barn

Day 4 – back of barn

Day 4 - trusses

Day 4 – trusses

Day 4 - inside of barn

Day 4 – inside of barn

Still waiting for the cupola to go on the top! That was one thing that I picked out for the barn. And, they called and convinced me to get an upgraded one, too! I can’t wait to see it. The excavator delivered some rock this morning for our driveway.

Driveway rock

Driveway rock

Now the pole barn guys can bring their truck in next week with a load of rock and spread inside the barn. After that they will put an insulation blanket down and then lay the pex tubing for the radiant heat floors. Then they can bring in the concrete truck and pour the pole barn floor.

I wish I could say that the house bid $$ were going as smooth as the pole barn did. They are not. 😥 The house is coming in way higher than it did last fall and we’ve already put (or will be putting out of our own money) close to $175K! We paid for the lot, all the light fixtures (inside and out), door hardware, laundry and kitchen cabinetry, the well, excavation costs, plumbing for pole barn (bath rough-in and radiant heat), and the pole barn. We went through the bids the other night with Jill after Bill and I had worked on them for a week line for line – Bill more than me this time. Turns out lumber has gone up almost double since J&J built. Jim’s brother did some checking and he said that even though the construction business is picking up, the lumber mills are still closed from the housing crash. Demand is more than supply.

We are trying to find some ways to cut the cost of the home we want to build without compromising the look and feel of it. We have found a couple of things – (siding and fireplace changes) to save some costs. Unfortunately, it’s not enough to make up the high lumber prices.

Next up: Will the expensive cupola be worth the wait and will we actually start building the house we want in July?

Status Change

You can’t stop the future
You can’t rewind the past
The only way to learn the secret
…is to press play.

~Jay Asher, Thirteen Reasons Why

I left you several days ago not knowing what would happen next. Wondering about those white SUV people. Wondering if we would show this house to anyone else. Wondering if we would sell this house. Well, we got the answers to all of those “wonderings” Wednesday and Thursday.

Let me set the stage . . . After I added my last post early Wednesday morning one of my online friends posted on Facebook that I should pray for peace instead of patience. I thought about this and it made perfect sense. If I prayed for patience, that meant I was asking God for me to wait and wait. If I prayed for peace within, I was asking God for calm and tranquility. So, I immediately started praying for peace (Thanks, Laura!) while I started to clean the house for the second showing that was scheduled for 4:45 that evening.

I have a cleaning system where I clean one level at a time and take a break in-between. We have a tri-level. I finished the top level and sat on our living room couch and checked my email on my iPhone. My eye immediately went to an email from our realtor entitled, “Offer on your home.” I started to read the email contents when the phone rang. It was our realtor. He wanted to make sure we had received the email he sent. I told him I was just starting to read it. He said Bill and I needed to read it all very carefully and call him back as soon as possible. I got in our Gator and drove back to the pole barn with my heart beating very fast. As soon as I saw Bill I excitedly said, “We got an offer! Get in! We need to read it and get back with Mike.”

Turns out it was an offer from the people with three children who had looked at our home on Sunday, May 19. It was a low offer. In addition, they were wanting closing cost money, too. But, it was an offer and the people really loved the place and wanted to raise their children in the home. They always say to work with the first good offer. Bill and I discussed how low we would go to sell the place. We were far apart in what we wanted and what they offered. After Bill and I talked, we called our realtor Mike. We were discussing our next steps when I heard a beep on the phone. I looked at the display and it was Centralized Showing Service. Really? I told Mike and he said to take the call and call him back.

It was a request to show our home that evening at 5:00-6:00 pm. We had the second showing people coming at 4:45-5:45. It was an automated phone call. Our options were to Accept, Decline, or Reschedule. I hit the Reschedule button. We were then routed to a live person. 🙂 The first thing I said was that we already had someone looking at the house during the time the realtor wanted to show it. The CSS guy said that the realtor was aware of that and still wanted to show our house at 5:00-6:00. I asked if realtors ever did that and he said yes. I asked if we could call them back after talking to our realtor. We weren’t sure what to do. We had the offer to deal with. We had a second showing coming. Do we invite another person in on the mix?

15142960-cartoon-question-mark-with-face-pondering-creativity-or-confused-about-test-answerWe called Mike back. He said, “I love buyers. The more the merrier. Let them come.” We thought why not. We will have the house clean. Get two for the price of one around the same time. That was settled. Then we started to talk about the offer. This was Wednesday morning. We had until Thursday evening at 7:00 to respond back to the offer. We all agreed on a price with which to counter the offer and decided that we would wait until the next day before making any final decisions. Mike said that he would call both real estate agents that evening after the showings to make them aware that we had received an offer that we could work with and if they were interested in the home they would have to act fast. We had a plan.

Bill and I hugged each other and went back to cleaning each of our areas – Bill to the pole barn, me to the mid level of the house. I got done cleaning around 3:00. I decided to run to the grocery and buy some cookie dough to make some cookies for the showings and to take some over to our neighbors as a thank you for letting us sit on their back patio that evening during the showings. Bill moved Goldie over to our neighbor’s yard and I came over after I did a second vacuuming of the house and turned on all the lights. Then we waited. Right before 4:45 we heard some car doors shutting. I think I was the one who went inside Alan’s (neighbor) house and looked out a window to see if the cars were at our house. Guess what? It was the white SUV people! 🙂 I felt those people must really be interested as not only was this their second showing, but we had seen them in front of our house several times since the first showing and once just a couple of days before.

We visited with Alan and their dogs safely hidden on the back patio. Goldie wandered in Alan’s yard on the side next to our house back and forth. You cannot see our house or our back yard when you are on the neighbor’s back patio. However, you can see the pole barn if you sit in one small area. That’s where Alan sat me with a chair. 😉 The white SUV people stayed in the house for about 30 minutes – until about 5:15. The other realtor still had not arrived. Then we heard a child squealing next door and people talking. We could hear them opening the shed. Then they walked out to the pole barn. The couple looked young. They had a baby and a boy around 4 years old. They had another gentleman with them besides the realtor. We figured it was one of the parents. After looking in the pole barn they returned to the house where they stayed until they left about 5:45. The other realtor still had not arrived!

By this time, I was ready to go home. But we couldn’t. We had to at least wait until after 6:00. At 5:55, the neighbor’s wife had just arrived home from work and she said two cars had just pulled into our driveway. Bummer! That meant it would be at least another 30 minutes before we could go back home and eat dinner. We had eaten all the cookies I brought! Alan told Rhonda they needed to go out into the back yard and start yelling at each other to dissuade anyone from buying our house. He had told us many times that they don’t want us to move. We laughed about the threat. We eventually heard people outside next door and I got a glimpse of them when they walked toward the pole barn. It was a couple with a toddler and the woman was pregnant. When they headed back to the house one of Alan’s dogs started barking. From the patio Alan yelled at Possum to come. But, she didn’t. Then, we heard a child giggling. Alan got up suddenly and went into the yard around the privacy fence to get Possum. Bill looked at me and then Rhonda (neighbor’s wife) and said, “Well, there goes the sale if Alan is out there talking to them!” 😆

We could not hear anything and Alan stayed out there for a while. When he came back to the patio he said, “They are really interested in your house!” He said they loved the place and loved having horses next door. They eventually left about 6:45. We gathered our belongings and Goldie and walked back home. Bill decided to call Mike and tell him about the last showing people and their interest. Mike said he would call both realtors around 8:30 that evening.

Mike called us about 9:00 to tell us what was going on. He said the white SUV people’s realtor had sent him two emails after the showing before Mike had a chance to call him. One email asked Mike to ask us why the kitchen faucet didn’t work; what was the gurgling noise when they turned on the small faucet in the kitchen; and where was the septic in the back yard. We told Mike everything was working fine and I had just used the faucet. It’s a lever type of faucet where you push back to get hot water and front to get cold. However, you must push the lever out to get the water to come out. Apparently, they had never pushed out! 🙄 And, the gurgling noise was the reverse-osmosis faucet and that’s just how it operates. Then Bill told Mike that there was a very visible riser in the back yard a few feet from our back patio to designate the septic. Mike said he was frustrated with that realtor. He said the other email said his clients planned to make an offer but they felt our list price was too high. This was the second time he had reported that. Mike said he would email the realtor back with our answers and to tell him about our other offer.

In the same phone conversation Mike said he had a voice-mail message from the realtor of last showing people and she wanted to know if we had already received an offer and how quickly could we move on this house as they were interested. OMG, you mean we had three different people interested in buying the place? In my wildest dreams I never imagined that would have happened to us. Mike said he tried to call the last realtor but she didn’t answer. He asked us how quickly we would be willing to move if it came down to that. Bill said if the price was right, we could move in three weeks! 😯 Notice, Bill said that, not me!

Mike blind cc’d us on the two separate emails he sent to the two realtors. Basically he said if they made an offer to make it their highest and best because he would not go back for a second round except for the first offer. And, if offers came in, he would tell the first people that we had multiple offers and they could choose to hold or make another offer.  Sounds a little like poker, doesn’t it?Wallingford-Real-Estate-Wallingford-PA-Multiple-Offers-Bidding-Wars

Talk about not sleeping Wednesday night! I purposely left my phone downstairs so I wouldn’t check my email all night long. But, even that didn’t help. I bet I slept two hours all night. At 7:30 Thursday morning, we received an email from Mike saying that he had a long talk with the last showing realtor. He said she had sent us a great offer. He said he was forwarding her cover letter. It went like this:

Hi Mike! As always, very nice talking to you!  Attached is a full price offer . . .

I got that far and screamed for Bill! Did I read that right? I suggested we go down to the desktop computer in the family room and pull up the email and the offer. It was true! They were offering us our full listing price but asking for $3000 in closing costs and the home warranty we had offered in our listing. The kicker was, they needed to close on the house on June 7 and wanted possession no later than 5:00 pm on June 10. That was less than three weeks away!

shocked_faceWell, Bill and I looked at each other and said that this was a no-brainer. Unless Mike thought there was a reason not to, we would accept this offer. We hugged each other and then quickly called Mike. We talked about how to handle the situation. What did we do about the first offer? After much discussion, Mike said that there was probably no way the first couple would come up to full price from what he gathered from the agent. So, we checked the Accept box, signed, dated, scanned and emailed the acceptance page to Mike. We checked the Reject box, signed, dated, scanned and emailed the rejection page to Mike from the first offer. OMG! We sold the house in two weeks after it was listed! Well, at least house listing status has changed from Active to Sale Pending.

Now, we just hope that the house appraisal and inspection go well. We don’t expect much wrong from the inspection as so much of major items are new. We already had a well inspection done before we put the house on the market. Bill emailed Mike to ask him if there were any special things he should check before the inspection. One of the items was electrical and the other was having the HVAC serviced and cleaned. So, Bill scheduled having a routine check-up on our 3-year old HVAC system done on Tuesday. Bill is switching out some electrical boxes/switches on any wall that might be close to water to meet a new code requirement, too. The inspection has been set for May 30. We got word yesterday that they are doing the appraisal tomorrow – on Memorial Day! Oh well, we’ll be here. And if everything goes well, we are set for the June 7 closing!

Bill and I went into panic mode on Thursday after we accepted the offer on the house. We called movers. We are tentatively on one mover’s schedule for June 6 and on another mover’s schedule for June 8. Both are coming out next week to give us estimates. We contacted both our children to tell them about the offer. Jim had some suggestions for Bill to see if there was any way we could get that pole barn built before we moved. That has not panned out. It will probably be the end of June or first of July before that will be done. But, Jim did find us an excavator for the pole barn and our new driveway. They will start that on June 3 if we don’t have rain delays.

Even though we know we have to pack up this house, we had to finalize our new house plans and specification document. Jim wants to send out bids this week. Bill and I spent about 5 hours on that Thursday evening. We still had some gaps of a few items before we could complete the specs. So, we dedicated Friday to settling on bathroom cabinets/vanities; granite for kitchen and bathrooms; and what to do about a safe room.

Here are pictures of the granite and bathroom cabinets:

This slideshow requires JavaScript.

Jim called us several times on Friday before and after they left town for the holiday weekend. Before he left town he asked me to email him what we had for our spec document so far so he could read over it while he was out-of-town. After we had gotten home from our all day vendor shopping day and stops at Home Depot to get more packing boxes and a new mailbox for our new place and Staples to get reinforced tape, Jim called us and wanted to talk. He had a long list of items we needed to do or which we had to make decisions. Jim was on the ball to get moving on our pole barn and house bids.

Bill decided he wanted to take one load down to Jim and Jill’s over the holiday weekend. J&J said we could store some things in their garage. Bill & I decided we did not want the movers to move any of the new cabinets Bill built or any of the items we purchased for the new house (lights fixtures, ceiling fans, door hardware, etc.). So, Bill and I worked a very long day Saturday in the pole barn. We dismantled, coded, and did some shrink wrapping of all the cabinets Bill had made. Then he wanted to move every thing we had stored in bins on one side of the storage area of the pole barn out into another area. He wanted to dismantle a large section of storage shelves so he could take them down and put up in J&J’s garage. I told him my way of organizing is only to move things one time. And, we needed to find a space where we could store the bins so the movers could get them. We cleared out a section of the pole barn and burned a lot of scrap wood. And, then we started to get out all those bins I had filled for almost two years.

Bill had started an inventory sheet for his boxes he started packing in the pole barn. I wanted to do the same. All of my bins were labeled. All I had to do was add a # to each box and write that # on an inventory sheet along with the box’s contents. We had a routine. Bill and I loaded bins on a table on wheels. Then we rolled them over to where Bill had set up two wooden work horses. I would quickly do the inventory and mark the appropriate # on the bin in several places, then Bill would take the bin and shrink-wrap it and then stack it. We did that over and over again. Some of those bins were heavy. We inventoried, shrink-wrapped, and stacked 44 bins! There are still a lot more on the other shelving unit! I had weeded through everything over the last two years and given away, sold, and trashed so much. I thought I was done. Haha. There are bins of things I’ll probably NEVER use. But, time is running short so we are moving them. Bill and I came up with the idea that the grandkids might want to go through all our unwanted things once we’ve moved and they can have a yard sale at our place. They can keep all the proceeds. Sounds like a plan! We’ll see if they like that plan. 🙂

Here are some photos of all the crazy things we dismantled and packed on the trailer and truck yesterday.

This slideshow requires JavaScript.

We were exhausted by the end of the day. Tylenol for me. Aleve for Bill. We both slept well last night.

The plan was for Bill to drive down to J&J’s early this morning; unload the shelving units; install the shelving units; unload all the items from the trailer and truck and store on the shelves; dig a hole and install the mailbox; and then drive back home. But, that’s not what happened. Bill got ready to go and drove the truck out to the pole barn to hook up the trailer. When he cranked the trailer hitch to the truck the truck really started to sink down. Bill knew he was at the maximum weight to pull. He looked at me and said, I can’t do this! 😯 He said he felt he just could not afford to spend a whole day gone with so much to do around here. I think he had hit his panic mode. I could see it in his face. He said he wanted to rent a storage unit around here and store all the stuff he wanted to move himself into it. That way he could move it down to J&J’s a little at a time and without rushing it in what is now a 2 week period. He knew I didn’t want to rent a storage unit up here. But, after thinking about it, it’s the best decision. We do not have time to travel over 3 hours both ways 4-5 times in the next two weeks. And, Bill is determined he will move certain things himself . . . period.

Bill decided he needed to work on the electrical stuff today. So that is what he has worked on all day. I spent about 3-4 hours on the specification document for the new house and finished it. Yay!!! I emailed it to Jim. But, here is what my computer area looked like while I was working.

House plans, spec document, catalogs, quotes

House plans, spec document, catalogs, quotes

I need to clean the house for the appraisal tomorrow, but found it difficult to clean when Bill was testing and turning off breakers. And, two of the boxes/switches he had to install were in the kitchen. Poor guy, he had a really tough time figuring out the wiring on those, but he finally did and they are done. While Bill was working inside on the electric, I cut the grass. It appears as I’m typing this that the outside boxes Bill is replacing are going a lot quicker than those inside ones. He has one more to do on the outside of the pole barn.

Folks, that’s where we are. I’m procrastinating cleaning with this blog post. Let’s just say that I haven’t run the vacuum cleaner since our last showing! Goldie’s been happy, but I need to clean. We need the appraisal to match the offer price. I don’t want to even think about what we have to do if it doesn’t. Prayers are welcome!!!

Next: You might not hear from me in a while if everything goes well. I’ll be so busy packing up what’s left in the house, outdoors, shed, and pole barn. June 10 is closer than I want to imagine.

Patience and a Gift from Above!

The two hardest tests on the spiritual road are the patience to wait for the right moment and the courage not to be disappointed with what we encounter. ~Paulo Coelho

Waiting and hoping is a hard thing to do when you’ve already been waiting and hoping for almost as long as you can bear it. ~Jenny Nimmo, Charlie Bone and the Time Twister

Today was worthy of a two-quoter! I’m trying to be patient with my lack of patience. 🙂

Our house is officially on the market. We listed it on Monday, May 6! It hit the MLS later Monday evening and was up with all the photos by Tuesday evening on all the sites. It’s Thursday and we haven’t had a showing yet. “Patience, Grasshopper!” The flyers aren’t out by the sign yet. Those are supposed to be delivered sometime today. I’m not sure of the statistics of whether flyers help or not. And, since I haven’t seen what they look like, it is hard for me to judge. Our realtor emailed yesterday and said that he hopes we get traffic this weekend. However, he cautioned us by saying since Sunday is Mother’s Day, it may be a slow weekend. He also said not to start worrying unless we’ve been through two weekends without any interest.

Here is the listing description:

This Home Has All The Best Of Country Living! This Sprawling 2.43 Acre Property Has A Huge Pole Barn With Storage Area, 200 Amp Service, And Heated. Open Floor Plan, Recently Remodeled Kitchen, 3 Seasons Porch, Skylights, New Roof, Gutters, Windows And Front Door 2012, New Hvac 2010. Newer Hardwood Floors, Reverse Osmosis Water System, The List Goes On And On! Quiet Country Living Near  Conveniences. You Must See This Home!

Here are some pics – most from the listing.

This slideshow requires JavaScript.

Today we are going to put down mulch around the trees. Other than that, we don’t have any other improvements to do – just maintenance. I’ve developed a quick house clean each morning and if I can keep it up, we shouldn’t be too stressed if and when we get a showing appointment.

Now, on to the news I promised I’d share about our new build.

A little back story first . . . Bill worked for a company years ago which was bought out by another company, which was bought out by another company, and so on and so on. Bill received paperwork every so often through the years from this company. About two years ago, Bill started to check to see if he was vested with this company. From everything he read, he thought you had to work 5 years to be vested. He called them and they sent him paperwork to say that he had worked 4 years, 11 months. So, Bill left it go . . . until about two months ago. He got to thinking that he had invested his own money through those 4 years, 11 months into a retirement plan there. So, he called again.

This time instead of asking how many years he had worked, he asked if he had money still there. The guy helping him said that not only did it look like he had some money there that he had invested, but it also appeared that he qualified for company retirement funds. Really? 😯 The guy couldn’t tell him how much he had, but said if Bill wanted to start receiving benefits, they would start the process and send him a packet in about two weeks. Honestly, Bill thought he might have a thousand dollars in there. And, with interests from the years it was there, it could be a little more. We were thrilled. Manna from heaven!

When the packet arrived in the mail, Bill opened it. The first page was a welcome to benefits page. Bill turned to page 2. It showed that he had invested $1,435.03 from 1979 to 4 years, 11 months after. Yay! Then, Bill turned to the next page and was totally shocked at what he saw. It turned out Bill qualified for Part A and Part B of a retirement fund. And, it was a nice substantial amount. OMG, OMG, OMG! Double and triple manna from heaven!

So, while we were down at Jill & Jim’s over Easter right after Bill retired, Bill hatched a great plan. He said since the manna from heaven was a gift from God, he would like to see if we could use that money outright to build our new pole barn now. It sounded like an answer to our prayers. If we could build the barn soon, it could solve a lot of problems for us. We could start moving stuff down there; we could have a place to store all our furniture and belongings while the house was being built; we could use part of the pole barn as an office for Bill while he is being General Contractor for our house construction; contractors could have a secure place to store their tools; Bill could continue to work on cabinets while the house was being built. And, we would not be financing the pole barn into our construction loan. And, that meant we would not have to take out as big a mortgage! 😀 Yes, it would solve a lot of things that were troubling us.

We got word last week that we got the permit to start building the pole barn!!!!

Yay!

Yay!

We notified Jim and he was going to re-draw the pole barn on our site plan and then remark the property where the pole barn and house will be located. And, he is supposed to be sending out bids for excavation. Hobgood Post Frames said they could begin constructing the barn two weeks after we have a pad. So, first will be surveying by Jim, followed by excavating bids. Then we break ground! We are also getting bids for heating, plumbing, and electric. Bill is going to use radiant heat cause he doesn’t like his feet getting cold while he’s working in his workshop.

Bill ordered the windows for the pole barn from Kight Lumber Center this week. We want the pole barn windows to match the exterior finish of the house windows – dark bronze. Kight had vinyl windows that were a perfect match. So, we are on our way. Another thing to check off our list!

There will be no stopping Bill from being down at the property while the pole barn is built. Whole process should take about 10 days. It will also be good for Bill to practice his General Contracting on our first project. Time will tell whether I’ll stay up here while that is happening or not. All depends on where we are in selling this place.

I’ll keep you posted!

Odds and Ends and Delays Already

Delay is the enemy of progress. ~Eliot Spitzer

Bill talked with the well driller (Scott) last night to confirm what time they would be drilling on Monday. Scott told him his truck was broke and they were trying to fix it, but he will not be able to drill on Monday. 😦 Unless there is a miracle repair today, we will have to reschedule the date until later in April. I asked Bill if he was sure Scott wasn’t playing an April Fool’s joke on him. He said, “No!” 🙄

Here are a few odds and ends:

  • A follower asked the square footage of the new house. Answer: Just under 2200 sq. ft. Contrary to what most people think, we did not downsize. 😯 Our present home is a little under 1700 sq ft. Everyone always thinks it’s larger when they get in here since it is a tri-level. If you notice on any of the floor plans I’ve shared, the new house will definitely be a one-story home. No stairs for these old bodies! 🙂
  • I signed up for Social Security on Tuesday this week. Knock on wood, so far my experience has gone a lot smoother than Bill’s. It started out a little rocky, but ended up okay. I had made an appointment for Tuesday at 9:00 am. I was told it would be a phone appointment and I would not need to go to the SS office. Worked for me. However, by 10:00 Tuesday, I had not received a phone call. I actually thought my phone wasn’t working, so I called the national SS phone number. They said someone would call me before 3:00 pm that day. Around noon I got a call from the downtown SS office with an apology that the office I was assigned to was short-handed that morning and no one had called me. It was all good and I was able to get all signed up. I should get my first check in April.
  • Regarding dental/vision insurance – After we had decided to not buy a dental and vision insurance or discount plan, Bill continued to search on the Internet. He found something about a discount plan that Delta Dental had for residents in certain states (Indiana, Michigan, and Ohio). For $80/year fee for a whole family, we could save an average of 20-40% on dental services, receive discounts on hearing care, and vision care. The cheapest discount plan we had looked at earlier was almost $600/year premium for both of us and they didn’t provide hearing with their plans. The deal on any of these discount plans is that you go to one of the participating doctors/services. We decided this would work for us and we enrolled. The $80 fee will pay for itself after one of us gets a cleaning. Thank you, Bill, for finding this. Thought I’d post about this in case others want to look into it. Here is the link: Delta Dental Direct of Indiana.

I forgot to share the kitchen cabinet scare we had last weekend. Bill had finished building the refrigerator cabinet and only had the cabinet to go above the refrigerator left to build. He decided to line up all the cabinets to mimic how they would look in our new kitchen so we could make sure everything was correct before he started building doors and drawers for the them.

When you look at the pictures below, note that Bill rested the small upper upper cabinets on top of the base cabinets and then the upper cabinets on top of them. Actually, the upper 36 inch wall cabinets will be mounted about 18 inches above the countertop, which is standard. And the upper upper 12 inch wall cabinets will be mounted above the upper cabinets. I wanted the cabinets to go up to the ceiling. There will be a 4-1/2 to 6 inch moulding to reach the ceiling – similar to Jill’s cabinets, but Bill is also adding a crown moulding. Obviously, I will never be able to reach those upper upper cabinets. The plan is to put LED lights in them and display something (not sure what yet) in each of them.

Here’s the funny (and scary) thing. When Bill invited me out to the pole barn Saturday afternoon to see the cabinets, I got so excited seeing them set up that I NEVER noticed that the set-up was all wrong! And, obviously, Bill thought they were right or he wouldn’t have set them up that way either. 😳

Bill decided to leave the cabinets set up so Jill and Jim could see them when they arrived later that day. Fast forward several hours and the four of us go back out to the pole barn. Bill, Jill and I were talking about what was going to be in each cabinet and then all of sudden I said, “Wait, this isn’t right! There is supposed to be a drawer cabinet on each side of the cooktop cabinet.” Like this:

Cabinet Set-up

Cabinet Set-up

Bill said, “No, I have it just like you printed out from the software.” He grabs the paper and looks at it and then sheepishly said, “Oops, I’ve got it wrong. I’ve got that base blind corner cabinet next to the cooktop cabinet.” We all just looked at each other in shock. Then, Jill says to me, “Mom, how didn’t you see this was wrong earlier today?” I started laughing and said, “I don’t know!” Then, I said to everyone, “How in the heck are we going to build a house if neither one of us got this right?”

Jill and Bill start talking about moving the cabinets to their correct positions and whether the corner cabinets were wrong AGAIN and Bill would have to remake them. I was sick for him. Really, I had a pit in my stomach. I didn’t want him to have to remake those cabinets. That meant he would have made them three times! Bill and Jill are two of a kind. They both have that engineer brain and can visualize things flipped and in order and how things connect. All those things that my mind cannot do. I walked away from the cabinets and started talking with Jim. Bill and Jill finally figured that Bill had to remake those corner cabinets again. 😦

Oh, this gets even better . . . Fast forward to the next morning. Jim had brought us those large professional print-outs of our house plans. Bill and I were the only ones up in the early morning. I’m looking through the house plans and realize that the way Bill had arranged those cabinets in the pole barn the day before didn’t match the house plans. When we flipped the house, the long run of cabinets with the cooktop was along the wrong wall. I get my cellphone and look at the photos I took of the cabinet set-up. The cabinet layout was supposed to look like this:

The correct cabinet layout

The correct cabinet layout

I quickly tell Bill about my findings. He comes over and looks at the house plans and looks at the photos. He said, “Well, maybe I did make the cabinets correct but lined them up wrong. Maybe I don’t have to make them over!” Now, I was even more worried about us building this house. 🙂 While the rest of us went to the Children’s Museum for the day, Bill stayed home and set-up the cabinets the correct way in the pole barn.

This slideshow requires JavaScript.

Turned out Bill didn’t have to re-make any of the cabinets. Yay!!